Construction Status (January, 2018) – Adelina, Bashundhara, Dhaka

Achievement Program for the month of December, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Parapet wall 100% 100% 20%
2 Wall tiles 100% 95% 5%
3 General floor tiles 50% 50% 50%
4 Grill fitting 50% 50% 50%
5 Roof top plaster + Others 100% 100% 50%
6 Cable wiring 100% 75% 25%
7 External plaster( E+N) 60% 80% 25%
8 Electrical wiring 100% 100% 15%
9 External plaster (E+N) 60% 60% 60%

Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 General floor tiles 95% 45%
2 Grill fitting 80% 30%
3 Roof top plaster + Others 100% 50%
4 Cable wiring 100% 100%
5 External plaster( E+N) 100% 40%
South 40% 40%
6 LCC 50% 50%
7 Boundary wall-West 100% 100%