Construction Status ( January, 2018) – Pinemont, UTTARA, DHAKA

Achievement Program for the month of December, 2017

SL NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 1st floor  roof slab and shuttering & re-bar work 100% 100% 5%
2 1st floor roof slab casting work 100% 100% 100%
3 2nd Floor Column Re-bar & Shuttering work 100% 100% 100%
4 2nd Floor Column casting work 100% 100% 100%
5 2nd floor  roof slab and shuttering & re-bar work 100% 100% 100%
6 2nd floor roof slab casting work 100% 100% 100%
7 GF Ceiling plaster 100% 50% 50%
8 I-Joist Removing work 100% 100% 50%
9 Temp site office construction 100% 100% 25%

Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 3rd Floor Column Re-bar & Shuttering work 100% 100%
2 3rd Floor Column casting work 100% 100%
3  3rd floor  roof slab and shuttering & re-bar work 100% 100%
4 3rd floor roof slab casting work 100% 100%
5 4th Floor Column Re-bar & Shuttering work 75% 75%
6 4th Floor Column casting work 75% 75%
7 GF Ceiling plaster 100% 50%