Construction Status (February, 2017) – Aspen, New Eskaton, Dhaka

bti - Project Construction Status (7)

Achievement for the month of January, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Internal paint, final coat simulteniously at all floors 100% 100% 10%
2 Tiles Pointing work at reception area 100% 90% 40%
3 Outside paint, final coat 100% 95% 15%
4 Fire pump installation 100% 95% 15%
5 Pavement tiles pointing 100% 90% 30%
6 Stair Tiles pointing 100% 95% 35%
7 Stair paint 2nd coat 100% 90% 50%

Program for the month of February, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Tiles Pointing work at reception area 100% 10%
2 Outside paint, final coat 100% 5%
3 Fire pump installation 100% 5%
4 Pavement tiles pointing 100% 10%
5 Stair Tiles pointing 100% 5%
6 Stair paint 2nd coat 100% 10%
7 Cleaning and handing over 100% 100%

Some of the project picture

outside-paint-final-coat

Front Image

logo-area-civil-work

Outside-paint-final-coat

internal-paint-final-coat-simulteniously-at-all-floors

Internal paint, final coat simultaneously at all floors

pavement-tiles-at-ground-floor

Pavement tiles at Ground floor

pavement-tiles-pointing

Pavement tiles pointing

stair-tiles-pointing

Stair-tiles-pointing

tiles-pointing-work-at-reception-area

Tiles-pointing-work-at-reception-area

fire-pump-installation

Fire-pump-installation