Construction Status (December, 2017) – Bonaire, Lalmatia, Dhaka

Achievement Program for the month of November, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Outside plaster 100% 100% 2%
2 Window grills 100% 100% 15%
3 Electrical cable wiring 100% 100% 5%
4 Facing bricks 100% 100% 10%
5 Floor tiles 100% 80% 10%
6 Boundary walls 50% 50% 50%
7 LCC works 80% 80% 80%
8 GF civil works 60% 60% 60%

Program for the month of December, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Floor tiles 100% 20%
2 Boundary walls 100% 50%
3 LCC works 100% 20%
4 GF civil works 100% 40%
5 Facing bricks 100% 100%
6 Aluminium works 20% 20%