Construction Status (January, 2018) – bti Landmark, Gulshan Avenue, Dhaka

Achievement Program for the month of December, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Drop wall construction work 100% 95% 5%
2 Fair Face Stair railing construction work at all floor 95% 75% 10%
3 Fair Face wall construction work at all floor 98% 98% 2%
4 Column plastering at all floor 100% 98% 3%
5 Ceiling Finishing at all floor 100% 98% 3%
6 Brick work at all floor 100% 98% 0%
7 Wall & Ceiling plaster at Stair 100% 90% 0%
8 Sanitary internal GI/PPR wiring work 90% 90% 10%
9 Sanitary UPVC vertical duct wiring work 85% 85% 20%
10 Wall Tiles work at all floor 60% 60% 30%
11 Floor Tiles work at all floor 60% 60% 20%
12 Deep tube well installation 5% 5% 5%


Program for the month of January, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Drop wall construction work 100% 5%
2 Fair Face Stair railing construction work at all floor 85% 10%
3 Fair Face wall construction work at all floor 100% 2%
4 Column plastering at all floor 100% 2%
5 Ceiling Finishing at all floor 100% 2%
6 Brick work at all floor 100% 2%
7 Wall & Ceiling plaster at Stair 100% 5%
8 Sanitary internal GI/PPR wiring work 95% 5%
9 Sanitary UPVC vertical duct wiring work 90% 5%
10 Wall Tiles work at all floor 70% 10%
11 Floor Tiles work at all floor 70% 10%
12 Deep tube well installation 100% 95%

Some of the project picture