Construction Status (January, 2018) – Dolly, Dhanmondi, Dhaka

Achievement Program for the month of December, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 9th floor roof slab shuttering done, casting 100% 100% 0%
2 9th floor column casting 100% 100% 50%
3 RCC works for Overhead Water Tank (OHT) 100% 0% 0%
4 !st Floor Internal plaster 100% 0% 0%
5 Ancilary works upto 3rd floor 100% 100% 100%

Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 9th floor roof slab  casting. 100% 100%
2 9th floor column casting 100% 50%
3 RCC works for Overhead Water Tank (OHT) 100% 100%
4 !st & 2nd Floor Internal plaster 100% 100%
5 Ancilary works at 4th & 5th floor 100% 100%
6 Electrical conduiting, 1st up to 3rd floor 100% 100%
7 Internal plaster, 1st floor 100% 100%