Construction Status (April, 2017) – Astoria, Baridhara, Dhaka

Achievement for the month of March, 2017

 

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 MS louver fittingwork at out side 100% 55% 5%
2 Internal Paint ( 1st coat) 100% 90% 15%
3 Internal Paint ( 2nd coat) 25% 25% 25%
4 GF Sewarage line work 100% 100% 5%
5 Aluminum work at all floor 75% 50% 5%
6 Wall tiles pointing work at floor 100% 100% 50%
7 Floor tiles pointing work at floor 75% 25% 0%
8 Door Shutter fitting at all floor 75% 75% 75%
9 Electric Switch-Socket fitting at all floor 70% 70% 70%
10 Sanitary ware fitting at all floor 10% 0% 0%
11 Pavement Tiles fitting at all floor 75% 75% 75%
12 Boundary wall construction 100% 100% 2%
13 Front area development work 100% 85% 10%


Program for the month April of, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 MS louver fittingwork at out side 100% 45%
2 Internal Paint ( 1st coat) 100% 10%
3 Internal Paint ( 2nd coat) 100% 75%
4 Aluminum work at all floor 75% 25%
5 Floor tiles pointing work at floor 75% 50%
6 Door Shutter fitting at all floor 100% 25%
7 Electric Switch-Socket fitting at all floor 100% 30%
8 Sanitary ware fitting at all floor 50% 50%
9 Pavement Tiles fitting at all floor 100% 25%
10 Front area development work 100% 15%