Construction Status (January, 2018) – Carnation, Baridhara, Dhaka

Achievement Program for the month of December, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Roof top area  plastering work 100% 100% 5%
2 Inside plaster at all floor 100% 100% 5%
3 Stair Room plaster at all floor 50% 50% 50%
4 Basement Ceiling & wall plaster 50% 50% 50%
5 Out Side plaster at all floor 50% 50% 25%
6 Facing Bricks at all Floor 25% 25% 25%
7 Cable wiring at all floor 10% 10% 10%
8 Wall Tiles work at all floor 95% 95% 15%
9 Window Grill fitting at all floor 10% 0% 0%
10 Floor Tiles work at all floor 10% 10% 10%
11 Boundary wall construction 10% 10% 10%

Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Stair Room plaster at all floor 100% 50%
2 Basement Ceiling & wall plaster 100% 50%
3 Out Side plaster at all floor 90% 40%
4 Facing Bricks at all Floor 50% 25%
5 Cable wiring at all floor 50% 40%
6 Wall Tiles work at all floor 98% 3%
7 Window Grill fitting at all floor 20% 20%
8 Floor Tiles work at all floor 50% 40%
9 LCC work 75% 75%
10 Ver Railing work at all floor 5% 5%
11 GF Brick work 50% 50%
12 Pavement tiles work at Basement & GF 15% 15%
13 Boundary wall construction 50% 40%

Some of the project picture