Construction Status ( January, 2018) – LAKE PANORAMA, UTTARA, DHAKA

Achievement Program for the month of December, 2017

 

SL NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 8th Floor Column shuttering & Re-bar work 100% 100% 75%
2 8th Floor Column casting work 100% 100% 75%
3 8th Floor roof shuttering and re-bar work 100% 100% 100%
4 8th Floor roof slab casting work 100% 100% 100%
5 Ceiling plaster work at (Completed up to 5th floor) to 6th & 7th floor 100% 100% 100%
6 Brick work at (completed up to 2nd Floor) 3rd floor 100% 100% 10%
7 Brick work at 4th floor 100% 100% 20%
8 Brick work at 5th floor 100% 100% 85%
9 Brick work at 6th floor 20% 100% 20%
10 Door Frame Fitting at 1st & 2nd floor 50% 50% 50%
11 Electric Conduit work at 1st & 2nd Floor 50% 50% 50%

Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 Roof top community hall roof slab casting 100% 100%
2 OHWT construction work 100% 100%
3 Front design beam casting 100% 100%
4 Roof ornamental comlumn casting 100% 100%
5 Ceiling plaster work at (Completed up to 7th floor) 8th floor 100% 100%
6 Brick work at (completed up to 4th Floor) 5th floor 100% 15%
7 Brick work at 6th floor 100% 100%
8 Brick work at 7th floor 100% 85%
9 Brick work at 8th floor 100% 100%
10 Door Frame Fitting at 1st & 2nd floor 100% 50%
11 Electric Conduit work at 1st & 2nd Floor 100% 50%
11 Sanitary Internal wiring work at all floor 20% 20%