Construction Status ( February, 2017) – Glen Grove, Chittagong

bti - Project Construction Status (7)

Achievement in the month of January, 2017

Sl No. Description of Works Program
for the month of
January – 2017
Achievement
for the month of
January – 2017
Overall achievement
up to this month
1 Stair tiles work 80% 50% 70%
2 Ground floor tiles work 80% 80% 100%
3 Aluminium door & window work (all floor) 25% 25% 100%
4 Catdoor shutter & moulding bit fitting 70% 70% 100%
5 Main door shutter fitting 100% 100% 100%
6 Internal door shutter fitting 100% 100% 100%
7 2nd floor inside paint up to 1st coat 100% 0% 0%
8 3rd floor inside paint up to 1st coat 100% 50% 50%
9 7th floor inside paint up to 1st coat 50% 50% 100%
10 8th floor inside paint up to 1st coat 100% 100% 100%
11 Sanitary ware & CP fittings fitting (all floor) 100% 0% 0%
12 Electrical switch-socket fitting (all floor) 100% 0% 0%
13 Inside paint up to 2nd coat (all floor) 50% 30% 30%
14 Wooden door polish except final finish (all floor) 50% 50% 50%
15 Tiles wash & pointing (all floor) 50% 0% 0%
16 Garden civil work 100% 100% 100%

Program for the month of February, 2017

Sl No. Description of Works Program
for the month of
February – 2017
Predicted
future achievement
up to February – 2017
1 Stair tiles work 30% 100%
2 Ground floor pavement tiles work 100% 100%
3 2nd floor inside paint up to 1st coat 100% 100%
4 3rd floor inside paint up to 1st coat 50% 100%
5 Sanitary ware & CP fittings fitting (all floor) 100% 100%
6 Electrical switch-socket fitting (all floor) 100% 100%
7 Inside paint up to 2nd coat (all floor) 40% 70%
8 Wooden door polish except final finish (all floor) 50% 100%
9 Tiles wash & pointing (all floor) 50% 50%

Some of the project picture

project-front-view-2

Front view 

project-front-view-3

Front view 2

Catdoor shutter & moulding bit fitting

Cat door shutter & mounding bit fitting

Garden civil work

Garden civil work

Ground floor tiles work

Ground floor tiles work

Inside paint up to 2nd coat (all floor)

Inside paint up to 2nd coat (all floor)

Internal door shutter fitting

Internal door shutter fitting

Main door shutter fitting

Main door shutter fitting

Stair tiles work

Stair tiles work

Wooden door polish except final finish (all floor)

Wooden door polish except final finish (all floor)

3rd floor inside paint up to 1st coat

3rd floor inside paint up to 1st coat

7th floor inside paint up to 1st coat

7th floor inside paint up to 1st coat

8th floor inside paint up to 1st coat

8th floor inside paint up to 1st coat

Aluminium door & window work (all floor)

Aluminium door & window work (all floor)