Construction Status (January, 2018) – Glendale, Uttara, Dhaka

Achievement Program for the month of December, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 GF civil works 100% 80% 40%
2 Internal plaster 100% 95% 5%
3 Electrical groove cut 100% 95% 5%
5 Vertical sanitary lines 70% 70% 70%
6 Bathroom wall tiles 100% 95% 5%
7 Bath floor tiles 50% 50% 50%
8 General floor tiles 100% 100% 20%
9 External plaster 100% 95% 45%
10 Window grills 100% 95% 20%
11 Verandah rails 50% 35% 35%
12 Outside rustic cladding 100% 95% 55%
13 Lime teracing 100% 100% 30%
14 Parking tiles 50% 0% 0%

Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 GF civil works 100% 20%
2 Internal plaster 100% 10%
3 Sanitary conduit wiring 100% 10%
5 Vertical sanitary lines 100% 30%
6 Bathroom wall tiles 100% 5%
7 Bath floor tiles 100% 50%
8 External plaster 100% 5%
9 Window grills 100% 25%
10 Verandah rails 100% 65%
11 Outside rustic cladding 100% 5%
12 Lime teracing 100% 30%
13 Roof top tiling 80% 80%
14 Stair tiling 50% 50%
15 Parking tiles 70% 70%
16 Thai aluminium works 40% 40%