Construction Status ( December, 2017 ) – The Accord, Dhanmondi, Dhaka

Achievement Program for the month of November, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Sanitary ware T-1 & 2 done, going on at T-3 100% 75% 25%
4 Switch, socket T-3 100% 100% 25%
5 Internal paint, T3 100% 100% 50%
6 Boundary wall works 100% 1oo% 10%
7 Sewarage works-T3 100% 100% 30%
8 GF wooden ceiling works 66% 66% 21%
9 External paint
10 Main gate, entry etc 100% 90% 15%

Program for the month of December, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Sanitary ware T-1 & 2 done, going on at T-3 100% 25%
2 Outside paint 75% 75%
3 Fitting fixing of switch socket 100% 10%
4 Sanitary ware fitting at all floor 100% 20%
5 Man gate, entries etcg 100% 10%
6 GF false ceiling works 100% 34%
7 T 3 main floor pointing 100% 100%

Some of the project picture