Construction Status (January, 2018) – Good Fortune, Uttara, Dhaka

Achievement Program for the month of December, 2017

SL NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 Internal Paint (1st coat) 100% 95% 70%
2 Out Paint work (1st Coat) 100% 75% 50%
3 Wall tiles pointing at all floor 50% 50% 50%
4 Stair Railing work 100% 100% 75%
5 GF Pavement tiles work 75% 75% 75%
6 Door shutter fitting at all floor 10% 10% 10%
7 Aluminum work at all floor 75% 75% 75%
8 Switch socket fitting at all floor 15% 15% 15%
9 Front area development work 90% 90% 5%
10 Boundary Safety Grill work 50% 50% 50%

Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 Internal Paint (1st coat) 100% 5%
2 Internal Paint (2nd coat) 50% 50%
3 Out Paint work (1st Coat) 100% 25%
4 Wall tiles pointing at all floor 100% 50%
5 GF Pavement tiles work 95% 20%
6 Door shutter fitting at all floor 90% 80%
7 Aluminum work at all floor 90% 15%
8 Switch socket fitting at all floor 90% 75%
9 Front area development work 95% 5%
10 Boundary Safety Grill work 100% 50%
11 Main gate fiitng 100% 100%
12 Sanitary ware fitting at all floor 25% 25%