Construction Status (December, 2017) – Paradiso, Uttara, Dhaka

Achievement Program for the month of November, 2017

PROGRAM UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 7th floor roof slab shuttering, rod fabrication & casting 100% 100% 100%
2 8th floor column shuttering, rod fabrication & casting 100% 100% 100%
3 6th floor ceiling plaster work 100% 100% 100%
4 Lintel & false slab at 3rd & 4th floor 100% 100% 100%
5 Brick work at 3rd & 4th floor 100% 80% 80%
6 Door frame fitting at 1st floor 100% 100% 100%
7 Wall plaster work at 1st floor 50% 50% 50%

Program for the month of December, 2017

SL. NO. DESCRIPTION OF WORK PROGRAM UP TO THIS MONTH PROGRAM IN THIS MONTH
1 8th floor roof slab shuttering, rod fabrication & casting 100% 100%
2 9th floor column shuttering, rod fabrication & casting 100% 100%
3 7th floor ceiling plaster work 100% 100%
4 Brick work at (completed up to 3rd floor) 4th floor 100% 25%
5 Brick work at 5th floor 10% 10%
6 Lintel & false slab(Completed up to 3rd floor) 4th floor 100% 100%
7 Door frame fitting at 3rd floor 100% 100%
8 1st floor wall plaster work 100% 100%
9 3rd floor wall plaster work 50% 50%

Some of the project picture