Construction Status (January, 2018) – Shopno Chura, Diabari, Uttara, Dhaka

Achievement Program for the month of December, 2017

SL NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 2nd floor column shuttering-rebar work (T-1) 100% 100% 20%
2 2nd floor column casting work (T-1) 100% 100% 20%
3 2nd floor roof re-bar & Shuttering work (T-1) 100% 85% 85%
4 2nd floor roof slab casting work (T-1) 100% 0% 0%
5 2nd floor roof slab shuttering & re-bar work (T-2) 100% 100% 0%
6 2nd floor roof slab casting work (T-2) 100% 100% 100%
7 2nd floor column shuttering-rebar work (T-3) 100% 100% 100%
8 2nd floor column casting work (T-3) 100% 100% 100%
9 2nd floor roof slab shuttering & re-bar work (T-3) 100% 100% 90%
10 2nd floor roof slab casting work (T-3) 100% 0% 0%
11 Ceiling plaster at GF 100% 100% 50%

Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 2nd floor roof re-bar & Shuttering work (T-1) 100% 15%
2 2nd floor roof slab casting work (T-1) 100% 100%
3 3rd floor column shuttering-rebar work (T-1) 100% 100%
4 3rd floor column casting work (T-1) 100% 100%
5 3rd floor column shuttering-rebar work (T-2) 100% 100%
6 3rd floor column casting work (T-2) 100% 100%
7 3rd floor roof slab shuttering & re-bar work (T-2) 100% 100%
8 3rd floor roof slab casting work (T-2) 100% 100%
9 2nd floor roof slab casting work (T-3) 100% 100%
10 3rd floor column shuttering-rebar work (T-3) 100% 100%
11 3rd floor column casting work (T-3) 100% 100%