Construction Status ( January, 2018) – SILVERENE, UTTARA, DHAKA

Achievement Program for the month of December, 2017

SL NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 Roof top tiles work 100% 100% 10%
2 Internal Paint (1st Coat) 50% 50% 25%
3 Internal Paint (2nd Coat) 25% 25% 25%
4 Floor Tiles work at all floor 100% 100% 5%
5 Boundary wall construction 100% 100% 20%
6 GF Sewarage line work 50% 50% 50%
7 GF Pavement tiles work 50% 30% 30%
8 Aluminm work at all floor 50% 50% 50%
9 Front area development work 50% 50% 25%
10 Door shutter fitting at all floor 30% 30% 30%
11 Switch- socket fitting at all floor 50% 50% 25%

Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 Internal Paint (1st Coat) 100% 50%
2 Internal Paint (2nd Coat) 75% 50%
3 Outside Paint (Rubbing) 100% 100%
4 Outside Paint (1st Coat) 50% 50%
5 GF Sewarage line work 100% 50%
6 GF Pavement tiles work 60% 30%
7 Open Trace area tiles work 100% 100%
8 Receptiom area tiles work 50% 50%
9 Aluminm work at all floor 80% 30%
10 Front area development work 100% 50%
11 Door shutter fitting at all floor 80% 50%
12 Switch- socket fitting at all floor 80% 30%
13 Door shutter fitting at all floor 80% 50%
14 Switch- socket fitting at all floor 80% 30%
15 Main Gate fitting work at all floor 100% 100%