Construction Status ( February, 2017) – Manor Royal, North Khulshi, Chittagong

bti - Project Construction Status (7)

Achievement for the month of January, 2017

Sl No. Description of Works Program
for the month of
Jan- 2017
Achievement
for the month of
Jan – 2017
Overall achievement
up to this month
1 2nd,3rd,4th,6th,7th,8th,10th & 11th floor all Main floor pointing work. 50% 100% 100%
2 Stair tiles pointing work 100% 100% 100%
3 6th,8th floor paint final coat work 50% 100% 100%
4 2nd,3rd,4th,,7th,,10th & 11th floor luxury paint work. 50% 50% 75%
5 Gardening work 100% 0% 0%
6 PDB connection work. 100% 0% 0%
7 Solar Fittings works. 80% 100% 100%
8 Out side weather  Final coat work. 50% 100% 100%
9 LOGO work 100% 0% 0%

Program for the month of  February, 2017

Sl No. Description of Works Program
for the month of Feb- 2017
Predicted
future achievement
up to Feb- 2017
1 2nd,3rd,4th,,7th,,10th & 11th floor luxury paint work. 25% 100%
2 Gardening work 100% 100%
3 PDB connection work. 100% 100%
4 LOGO work 100% 100%
5 Water purification plant work. 100% 100%
6 North side drainage work 100% 100%

Some of the project picture

Out side weather Final coat work.

Front view

2nd,3rd,4th,6th,7th,8th,10th & 11th floor all Main floor pointing work.

2nd,3rd,4th,6th,7th,8th,10th & 11th floor all Main floor pointing work6th,8th floor paint final coat work

6th,8th floor paint final coat work

Solar Fittings works.

Solar Fittings works

Stair tiles pointing work

Stair tiles pointing work

2nd,3rd,4th,,7th,,10th & 11th floor luxury paint work.

2nd,3rd,4th,,7th,,10th & 11th floor luxury paint work