Construction Status (December, 2017) – Talukder Lodge, Kalabagan, Dhaka

Achievement for the month of November, 2017

SL  NO DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 Brick work at all fl 100% 100% 10%
2 Lintel,false slab at at all floor 100% 90% 5%
3 Door frame 100% 80% 5%
4 Inside plaster, all floor 90% 90% 10%
5 Electrical conduiting 90% 90% 10%
6 Roof top works 100% 100% 30%

Program for the month of December, 2017

SL  NO DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
2 Lintel,false slab at at all floor 100% 10%
3 Door frame 100% 20%
4 Inside plaster, all floor 100% 10%
5 Electrical conduiting 100% 10%
6 Roof top works 100% 30%
7 Sanitary wiring 50% 50%