Construction Status (February, 2017) – The Galaxy, Panchlaish, Chittagong

bti - Project Construction Status (7)

Achievement for the month of January, 2017

Sl No. Description of Works Program for the month of

January-2017

Achievement for the month of January-2017 Overall achievement up to this month
1 Inside paint work (2nd coat) 10% 5% 95%
2 Inside paint work final coat (3rd coat) 100% 25% 25%
3 Out side paint work  (2nd coat) 50% 20% 70%
4 General floor tiles pointing work 30% 20% 70%
5 Gardening work front side 100% 00% 00%
6 Roof top final paint work 100% 50% 50%
7 Front side logo work 100% 00% 00%
8 Roof top artificial grass  fitting 100% 00% 00%
9 Roof top roofing compound paint work 100% 50% 50%
10 2nd basement pavement tiles pointing 100% 00% 00%
11 Door shutter polish final coat 100% 50% 50%

Program for the month of  February, 2017

Sl No. Description of Works Program for the month of

February -2017

Predicted future achievement up to February-2017
1 Inside paint work (2nd coat) 5% 100%
2 Inside paint work final coat (3rd coat) 100% 100%
3 Outside paint work  (2nd coat) 30% 100%
4 General floor tiles pointing work 30% 100%
5 Gardening work front side 100% 100%
6 Roof top final paint work 30% 100%
7 Front side logo work 100% 100%
8 Roof top artificial grass  fitting 100% 100%
9 Roof top roofing compound paint work 50% 100%
10 2nd basement pavement tiles pointing 100% 100%
11 Door shutter polish final coat 20% 100%

Some of the project picture

IMG_0015

Front view

Door shutter polish final coat

Door shutter polish final coat

General floor tiles pointing work

General floor tiles pointing work

Inside paint work (2nd coat)

Inside paint work (2nd coat)

nside paint work final coat (3rd coat)

snide paint work final coat (3rd coat)

Roof top final paint work

Roof top final paint work

Roof top roofing compound paint work

Roof top roofing compound paint work

Out side paint work (2nd coat)

Out side paint work (2nd coat)