Property/Project Construction Status

The status of our projects under construction is updated in this section regularly. Here we provide the details of all our projects that are under construction. Contact us for additional information on the project’s construction status, in which we will include a brief write-up.

Construction Status / June 21, 2017

Construction Status – Shopnobilash, Savar, Dhaka

Construction Status / June 15, 2017

Construction Status (June, 2017) Fairmont, Lalmatia, Dhaka

Construction Status / June 15, 2017

Construction Status (June, 2017) – The Orient, Chittagong

Construction Status / June 14, 2017

Construction Status (June, 2017) – Glendale, Uttara, Dhaka

Construction Status / June 12, 2017

Construction Status (June, 2017) – Dolly, Dhanmondi, Dhaka

Construction Status / June 10, 2017

Construction Status (June, 2017) – Aplomb, Uttara, Dhaka

June 21, 2017 // 10:30 am

Construction Status (June, 2017) – Chayabithi, Uttara, Dhaka

Achievement in the month of May, 2017

SL  NO DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 4th floor column shuttering, rod fabrication & casting at tower-1&2 100% 100% 100%
2 4th floor roof slab shuttering and casting 100% 100% 100%
3 Brick work at all floor, 1st floor ongoing 10% 10% 5%
4 Ceiling plaster, Ground floor ongoing 5% 5% 5%

PROGRAM FOR THE MONTH OF June, 2017

SL  NO DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 5th floor column shuttering, rod fabrication & casting at tower-1&2 100% 100%
2 5th floor roof slab shuttering and casting 100% 100%
3 Brick work at all floor, 1st floor ongoing 15% 5%
4 Ceiling plaster, Ground floor ongoing 10% 5%

Some of the project picture

Front View

IMG_2858

Building Side View

IMG_2857

South Side

IMG_2859

Brick work at all floor, 1st floor ongoing

IMG_2866

Ceiling plaster, Ground floor ongoing

IMG_2860

4th floor roof slab shuttering and casting

IMG_2861

4th floor column shuttering, rod fabrication & casting at tower-1&2

IMG_2862

4th floor roof slab shuttering and casting

IMG_2864


June 15, 2017 // 10:33 am

Construction Status ( June, 2017 ) – Sattar Manzil,K B Abdur Sattar Rd, Rohomotgong, Chittagong

Achievement Program for the month of May, 2017

Sl No. Description of Works Program
for the month of
May -2017
Achievement of May -2017 Overall achievement up to this month
1 Shuttering rebar binding & casting of 1st floor roof 50% 50% 100%
2 Shuttering rebar binding & casting of 6th floor slab 50% 50% 50%
3 Rebar binding shuttering & casting of 6th floor column 50% 50% 50%
4 Rebar binding shuttering & casting of 2nd floor column 50% 30% 80%
5 Brick layout 1st floor 50% 10% 10%
6 Brick layout 2nd floor 50% 0% 0%
7 Celing plaster 2nd floor 50% 0% 0%
8 Celing plaster 3rd floor 50% 0% 0%

Program for the month of  June, 2017

Sl No. Description of Works Program
for the month of
JUNE/2017
Predicted
future achievement
up to MAY/2017
1 Rebar binding, shuttering & RCC Casting of 2nd floor roof 50% 50%
2 Rebar binding, shuttering & RCC Casting of 6th floor roof 50% 0%
3 Rebar binding,shuttering & Rcc casting of 7th floor column 50% 0%
4 Rebar binding,shuttering & casting of 2nd floor column 20% 80%
5 Brick layout 2nd floor 50% 0%
6 Brick layout 3rd floor 50% 0%
7 Brick work 2nd & 3rd floor 50% ( Each floor) 0%
8 Celing plaster ground floor 50% 50%
9 Celing plaster 1st floor 75% 25%

Some of the project picture

Shuttering rebar binding & casting of 6th floor slab

Shuttering rebar binding & casting of 6th floor slab

Rebar binding shuttering & casting of 2nd floor column

Rebar binding shuttering & casting of 2nd floor column

Rebar binding shuttering & casting of 6th floor column

Rebar binding shuttering & casting of 6th floor column


June 15, 2017 // 10:29 am

Construction Status ( June, 2017 ) – New Haven, Panchlaish R/A, Chittagong

Achievement Program for the month of May, 2017

Sl No. Description of Works Program
for the month of May-17
Achievement
for the month of  May-17
Overall achievement

up to this month

1 R.C.C Pile casting 40% 100% 50%

Program for the month of  June, 2017

Sl No. Description of Works Program
for the month of
June-2017
Predicted
future achievement
up to June-2017
1 R.C.C Pile casting 50% 100%

Some of the project picture

Project Front View

IMG_0009

R.C.C Pile casting

R.C.C Pile casting 1


June 15, 2017 // 12:00 am

Construction Status (June, 2017) Fairmont, Lalmatia, Dhaka

Achievement Program for the month of May, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 7th floor column shuttering and casting 100% 100% 100%
2 7th floor roof slab casting 100% 100% 100%
3 Brickwork at all floors, upto 3rd floor completed, above floors ongoing 30% 30% 10%
4 Ceiling plaster upto 4th floor completed, above floors ongoing, 20% 20% 5%

Program for the month of June, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Roof top RCC works 50% 50%
2 Parapet work 50% 50%
3 Brickwork at all floors, upto 4th floor completed, above floors ongoing 40% 10%
4 Ceiling plaster upto 5th floor completed, above floors ongoing, 30% 10%
5 Door frame fitting ongoing 10% 10%
6 Electrical groove cutting ongoing 10% 10%

Some of the project picture

Front Image

IMG_4753

7th floor column shuttering and casting

6th floor column shuttering and casting

7th floor roof slab casting

6th floor roof slab casting

Brickwork at all floors, upto 3rd floor completed, above floors ongoingIMG_2949

Ceiling plaster, 4th floor ongoing

IMG_2948


June 15, 2017 // 12:00 am

Construction Status (June, 2017) – The Orient, Chittagong

Achievement for the month of May, 2017

 

SL

 

Description of Works

Program for the month of

  May-2017

Achievement  for the month of  may-2017 Over all achievement up to this month
1 Bolli drive work for UGWR and lift core work purpose. 100% 100% 100%
2 UGWR casting work up to ground floor. 100% 40% 40%
3 Lift core casting work up to ground floor. 100% 40% 40%
4 Column casting up to ground floor. 40% 40% 40%
5 Staircase casting up to ground floor. 100% 00% 00%
6 Earth filling up to Parking level. 40% 40% 40%

Monthly Program for the month of June, 2017

 

SL

 

Description of Works

Program for the month of

     JUNE-2017

Predicted future achievement up to JUNE-2017
1 UGWR casting work up to ground floor . 60% 100%
2 Lift core casting work up to ground floor.          50%          50%
3 Grade beam casting. 60% 100%
4 Staircase casting up to ground floor. 50% 50%
5 Slab & beam shuttering work. 50% 50%
6 Slab & beam rod fabrication work. 100% 100%
7 Slab casting work 50% 50%

IMG_0006 Some Project pictures

Front view

Bolli drive work for UGWR and lift core work purpose.

Bolli drive work for UGWR and lift core work purpose.

Column casting up to ground floor.

Column casting up to ground floor.

Earth filling up to Parking level.

Earth filling up to Parking level.

Lift core casting work up to ground floor.

Lift core casting work up to ground floor.

UGWR casting work up to ground floor.

UGWR casting work up to ground floor.

Foundation work (Earth excavation, pile head broken, pile cap, short column, UGWT, septic tank casting etc.


June 15, 2017 // 12:00 am

Construction Status (June, 2017) – My Forte, Lalmatia, Dhaka

Achievement for the month of May, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 7th floor roof casting 100% 100% 100%
2 Brickwork, upto 3rd floor completed, above floor ongoing 30% 30% 5%
3 Ceiling plaster, upto 4th floor completed, above floor ongoing 40% 40% 10%
4 Lintel false slab 1st floor completed, other floors ongoing 15% 15% 5%

Program for the month of June, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 8th floor column casting 100% 100%
2 8th floor roof shuttering 80% 80%
3 Brickwork, upto 4th floor completed, above floor ongoing 40% 10%
4 Ceiling plaster, upto 5th floor completed, above floor ongoing 50% 10%
5 Lintel false slab up to 2nd floor completed, other floors ongoing 15% 5%
6 Door frame fitting ongoing 15% 15%
7 Electrical groove cutting ongoing 15% 15%
8 Internal plaster, ongoing 15% 15%

Some of the project picture

Front imageIMG_4756

Back Side

IMG_4755

7th Floor Roof Slab

Roof Slab

Ceiling plaster, upto 4th floor completed, above floor ongoing

IMG_2956

Brickwork, upto 3rd floor completed, above floor ongoing

IMG_2960

Ceiling plaster, upto 3rd floor completed, above floor ongoing

Ceiling plaster, upto 3rd floor completed, above floor ongoing

Lintel false slab 1st floor completed, other floors ongoing

Lintel work ongoing from 1st floor


June 14, 2017 // 12:00 am

Construction Status (June, 2017) – Glendale, Uttara, Dhaka

Achievement in the month of May, 2017

SL NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 Ceiling plaster work, 7th floor completed others ongoing 80% 80% 20%
2 Lintel & false slab casting, 5th floor ongoing 60% 60% 10%
3 Brick work, upto 5th floor completed others ongoing 60% 60% 10%
4 Door frame fitting up to 3rd floor completed 40% 40% 20%
5 Internal plaster, 2nd floor ongoing 20% 20% 10%
6 Electrcial groove cutting, 1st, 2nd & 3rd completed, above floor ongoing 40% 40% 10%

Program for the month of June, 2017

SL. NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 Ceiling plaster work, 8th floor ongoing 100% 20%
2 Lintel & false slab casting, upto th floor completed 70% 10%
3 Brick work, upto 5th floor completed, 7th & 8th floor ongoing 80% 10%
4 Door frame fitting up to 4th floor completed 50% 10%
5 Internal plaster, 4th floor ongoing 40% 20%
6 Electrcial groove cutting, upto 4th floor completed 50% 10%
7 Sanitary & plumbing work, 1st & 2nd floor completed 20% 20%
8 Bathroom wall tiles will be started from 1st floor 20% 20%

Some of the project pictures

Front Image

Front image

Brick work, upto 5th floor completed others ongoing

IMG_2856

Internal plaster, 2nd floor ongoing

IMG_2855

Parapet casting

Parapet casting

Brick work, upto 4th floor completed others ongoing

Brick work, upto 4th floor completed others ongoing

Ceiling plaster work, 6th floor completed others ongoing

Ceiling plaster work, 6th floor completed others ongoing

Door frame fitting up to 2nd floor completed

Door frame fitting up to 2nd floor completed

False slab casting, 4th floor completed others ongoing

False slab casting, 4th floor completed others ongoing

Internal plaster, 2nd floor ongoing

Internal plaster, 2nd floor ongoing

Lintel 4th floor completed others ongoing

Lintel 4th floor completed others ongoing


June 14, 2017 // 12:00 am

Construction Status (June, 2017) – Astoria, Baridhara, Dhaka

Achievement for the month of May, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 MS louver fittingwork at out side 100% 98% 8%
2 Internal Paint ( Final coat) 50% 50% 50%
3 Aluminum work at all floor 90% 90% 15%
4 Floor tiles pointing work at floor 100% 100% 25%
5 Sanitary ware fitting at all floor 100% 100% 50%
6 Pavement Tiles fitting at all floor 100% 100% 10%
7 Front area development work 100% 98% 8%
8 GF safety grill fitting work 75% 75% 75%
9 Open trace work 100% 75% 75%
10 GF false ceiling work 100% 75% 75%
11 CRD visit for obsrvation & rectification 75% 75% 75%

Program for the month of June , 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 MS louver fittingwork at out side 100% 2%
2 Internal Paint ( Final coat) 100% 50%
3 Aluminum work at all floor 100% 10%
7 Front area development work 100% 2%
8 GF safety grill fitting work 100% 25%
9 Open trace work 100% 25%
10 GF false ceiling work 100% 25%
11 CRD visit for obsrvation & rectification 100% 25%

Some of the project picture

Front ImageFront Image

Front area development work

Front area development work

GF false ceiling work

GF false ceiling work

GF safety grill fitting work

GF safety grill fitting work

Internal Paint ( 2nd coat)

Internal Paint ( 2nd coat)

MS louver fittingwork at out side

MS louver fittingwork at out side

Pavement Tiles fitting at all floor

Pavement Tiles fitting at all floor

Sanitary ware fitting at all floor

Sanitary ware fitting at all floor

Aluminum work at all floor

Aluminum work at all floor

Floor tiles pointing work at floor

Floor tiles pointing work at floor


June 13, 2017 // 4:12 pm

Construction Status (June, 2017) – The Unity, Halishahor, Chittagong

Achievement in the month of May, 2017

SL NO Description of works Program for the month May     of  -2017 Predicted Future Achievement up to

May   -2017

Overall achievement up to this month
1 8th floor  pvc conduit laying 100% 100% 100%
2 7th floor cable wiring 100% 100% 100%
3   Roof top GI wiring 100% 0% 0%
4 Ground floor 4” pvc  horizental wiring 100% 100% 100%
5 Sink & shower tray fitting 1st floor to 4th floor 100% 100% 100%
6 Out site plaster A type south side 100% 100% 100%
7 Out site plaster  B type north  side 100% 50% 50%
8 Void plaster type A& B 100% 100% 100%
9 Void plaster type E & D 100% 50% 50%
10 Roof top paten stone 100% 0% 0%
11 Fire door south wall plaster 100% 0% 0%
12 8th floor door frame fittings 100% 100% 100%
13 All common  area grill fitting 100% 100% 100%
14 False slab pvc surrounding plaster 100% 100% 100%

PROGRAM FOR THE MONTH OF June, 2017

SL NO Description of works Program for the month June  of  -2017 Predicted Future Achievement up to

June   -2017

1 8th floor wall plaster 100% 100%
2 Void plaster C& D Unit 100% 100%
3 Type A&B unit verandah plaster 100% 100%
4 Roof top Patten stone 100% 100%
5 1.25”bath waist pipe fitting 100% 100%
6 8th floor MK box fitting 100% 100%
7 Roof top GI wiring 100% 100%

Some Project PicturesIMG_0012

Front View

Out site plaster B type north side

Out site plaster B type north side

Out site plaster A type south side

Out site plaster A type south side

Sink & shower tray fitting 1st floor to 4th floor

Sink & shower tray fitting 1st floor to 4th floor

Void plaster type A& B

Void plaster type A& B

All common area grill fitting

All common area grill fitting

8th floor door frame fittings

8th floor door frame fittings

8th floor pvc conduit laying

8th floor pvc conduit laying7th floor cable wiring

7th floor cable wiring