Property/Project Construction Status

The status of our projects under construction is updated in this section regularly. Here we provide the details of all our projects that are under construction. Contact us for additional information on the project’s construction status, in which we will include a brief write-up.

Construction Status / October 16, 2017

Construction Status (October, 2017) – Paradiso, Uttara, Dhaka

Construction Status / October 15, 2017

Construction Status ( October, 2017) – Pinemont, Uttara, Dhaka

Construction Status / October 15, 2017

Construction Status ( October, 2017) – FLORENCE, UTTARA, DHAKA

Construction Status / October 15, 2017

Construction Status (October, 2017) – Bonaire, Lalmatia, Dhaka

Construction Status / October 15, 2017

Construction Status (October, 2017) – Aplomb, Uttara, Dhaka

Construction Status / October 15, 2017

Construction Status (October, 2017) – Glendale, Uttara, Dhaka

Construction Status / October 15, 2017

Construction Status (October, 2017) – Dolly, Dhanmondi, Dhaka

Construction Status / September 15, 2017

Construction Status ( October, 2017) – Armitage, Banani, Dhaka

October 16, 2017 // 2:01 pm

Construction Status ( October, 2017) – Southern Heights,Uttara,Dhaka

Achievement Program for the month of September, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Grade beam work 100% 100% 10%
2 Ground floor column 100% 100% 30%
3 Ground floor roof slab 100% 100% 100%

Program for the month of October, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 1st floor column 100% 100%
2 1st floor roof slab 100% 100%
3 Ground floor ceiling plaster 100% 100%

Some of the project pictures

Front Image

IMG_3205

1st Floor Coloum Casting

IMG_1276

1st Floor Roof casting

IMG_1273


October 15, 2017 // 12:24 pm

Construction Status ( October, 2017) – Chhayabithi ,Uttara, Dhaka

Achievement Program for the month of September, 2017

SL  NO DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 5th floor column shuttering, rod fabrication & casting at tower-1&2 100% 100% 100%
2 5th floor roof slab shuttering and casting 100% 100% 100%
3 Brick work at all floor, 1st floor ongoing 15% 15% 5%
4 Ceiling plaster, Ground floor ongoing 10% 10% 5%

Program for the month of October,2017

SL  NO DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 6th floor column casting 100% 100%
2 7th floor roof slab shuttering and casting 100% 100%
3 Brick work at all floor, 1st floor ongoing 20% 5%
4 Ceiling plaster, 1st floor ongoing 15% 5%

Some of the project pictures

Front image

IMG_2859

Ceiling Plaster

IMG_2016

Roof Slab Shuttering

IMG_2013

Brick Work

IMG_2017


October 15, 2017 // 11:44 am

Construction Status (October, 2017) – Shopnobilash,Savar, Dhaka

bti-Project-Construction-Status-7

Achievement Program for the month of September, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Mobilization work 100% 100% 100%
2 Building Layout work 100% 100% 100%
3 Building Layout checking work 100% 100% 100%

Program for the month of October, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Earth work in Excavation (1st phase) 10% 10%
2 Footing work shuttering, re-bar & casting work 5% 5%

Some of the project picture

Front View

IMG_1362 IMG_1341

Earth Excavation

IMG_1345 IMG_1346 IMG_1350

IMG_1352


October 15, 2017 // 12:00 am

Construction Status (October, 2017) – Bonaire, Lalmatia, Dhaka

Achievement for the month of September, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Outside plaster, north side completed, front side & south side ongoing 75% 65% 5%
2 Front verandah railing work 50% 30% 30%
3 Window grill fitting 50% 30% 30%
4 Bathroom and kitchen wall tiles 90% 90% 90%
5 Electrical cable pulling 50% 50% 50%
6 Fitting fixing of facing bricks 10% 10% 10%

Program for the month of October, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Outside plaster, north side completed, front side & south side ongoing 75% 10%
2 Front verandah railing work 100% 70%
3 Window grill fitting 75% 25%
4 Bathroom and kitchen wall tiles 100% 10%
5 Electrical cable pulling 100% 50%
6 Fitting fixing of facing bricks 100% 90%
7 General floor tiles fitting 40% 40%
8 Ceiling rubbing before fitting fixing of general floor tiles 50% 50%

Some of the project picture

Front View

IMG_4754

Var. railing

IMG_2130

Electrical cable pulling

IMG_2129

Bathroom wall tiles

Bathroom and kitchen wall tiles

Electrical cable pulling

Electrical cable pulling

Fitting fixing of facing bricks

Facing brickwork

Outside plaster, north side completed, front side & south side ongoing

Outside plaster


October 15, 2017 // 12:00 am

Construction Status (October, 2017) – Aplomb, Uttara, Dhaka

Achievement Program for the month of September, 2017

6 Boundary wall construction work 100% 100% 5%
7 GF Sewerage line construction work 100% 100% 25%

Program for the month of October, 2017

SL. NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 Internal Paint (1st coat) at all floor 25% 25%
2 Internal Paint (2nd coat) at all floor
3 Outside Paint work (1st coat) 50% 50%
4 Door shutter fitting at all floor 50% 50%
5 Electric Switch Socketing fitting 50% 50%
6 Aluminum work 50% 50%
7 Stair Railing fitting work at all floor 100% 100%
8 Boundary Safety grill work 100% 100%
9 GF False Ceiling work 50% 50%
10 GF Pavement Tiles work 100% 75%
11 Front area development work 75% 50%

Some of the project pictures

Front Image

IMG_0324

Floor Tiles

IMG_1967

Boundary Wall Cons. Ongoing

IMG_1966


October 15, 2017 // 12:00 am

Construction Status (October, 2017) – Glendale, Uttara, Dhaka

Achievement Program for the month of September, 2017

SL NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 Ceiling plaster work, 8th floor completed others ongoing 80% 80% 20%
2 Lintel & false slab casting, 6th floor ongoing 60% 60% 10%
3 Brick work, upto 6th floor completed others ongoing 60% 60% 10%
4 Door frame fitting up to 3rd floor completed 40% 40% 20%
5 Internal plaster, 2nd floor ongoing 20% 20% 10%
6 Electrcial groove cutting, 1st, 2nd & 3rd completed, above floor ongoing 40% 40% 10%

Program for the month of October, 2017

SL. NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 Ceiling plaster work, 8th floor ongoing 100% 20%
2 Lintel & false slab casting, upto th floor completed 70% 10%
3 Brick work, upto 5th floor completed, 7th & 8th floor ongoing 80% 10%
4 Door frame fitting up to 4th floor completed 50% 10%
5 Internal plaster, 4th floor ongoing 40% 20%
6 Electrcial groove cutting, upto 4th floor completed 50% 10%
7 Sanitary & plumbing work, 1st & 2nd floor completed 20% 20%
8 Bathroom wall tiles will be started from 1st floor 20% 20%

Some of the project pictures

PPR

IMG_3124

Brick Work

IMG_3128

Wall Tiles

IMG_3125

Electrical Goove cutting

IMG_3127

Door Shutter Fitting

IMG_3121

Internal Plaster

IMG_3123


October 15, 2017 // 12:00 am

Construction Status (October, 2017) – Bti Landmark, Gulshan Avenue, Dhaka

Achievement Program for the month of September, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Sanitary internal GI/PPR wiring work 100% 100% 2%
2 Sanitary UPVC vertical duct wiring work 100% 100% 2%
3 Wall Tiles work at all floor 90% 90% 10%
4 Floor Tiles work at all floor 85% 85% 5%
5 Patent stone work at parking area 100% 95% 5%
6 STP & WTP Civil work construction work 100% 90% 20%
7 Fair Face finishing work 10% 10% 10%
8 Sub-station & Generator room construction 100% 50% 50%
9 Glass curtain wall work (Shop Drawing prepartion & Approval) 100% 100% 25%
10 Boundary wall construction work 25% 0% 0%
11 Front water body construction work 25% 0% 0%
12 Internal duct B/W and Plaster work 75% 75% 75%
13 Roof top AC base construction work 100% 0% 0%
14 LCC work 25% 10% 10%
15 Fire Hydrent & Water Sprinkler work 25% 15% 15%
16 Fire Alarm  work 5% 5% 5%

Program for the month of October, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Sanitary GI/PPR wiring work at roof top area 10% 10%
2 Wall Tiles work at all floor 95% 5%
3 Floor Tiles work at all floor 90% 5%
4 Patent stone work at parking area 100% 5%
5 STP & WTP Civil work construction work 100% 10%
6 Fair Face finishing work 25% 15%
7 Sub-station & Generator room construction 100% 50%
8 Glass curtain wall work Survey & BOQ etc. work 25% 25%
9 Boundary wall construction work 25% 25%
10 Front water body construction work 25% 25%
11 Internal duct B/W and Plaster work 100% 25%
12 Roof top AC base construction work 100% 100%
13 LCC work 40% 25%
14 Fire Hydrent & Water Sprinkler work 50% 25%
15 Fire Alarm  work 10% 5%

Some of the project picture

Front view

IMG_1091

Roof top AC base construction work

Roof top AC base construction work

Glass curtain wall

Glass curtain wall

Fire Hydrent & Water Sprinkler work

Fire Hydrent & Water Sprinkler work

Internal duct BW and Plaster work

Internal duct BW and Plaster work

Patent stone work at parking area

Patent stone work at parking area

Wall Tiles

Wall Tiles work at all floor