Property/Project Construction Status

The status of our projects under construction is updated in this section regularly. Here we provide the details of all our projects that are under construction. Contact us for additional information on the project’s construction status, in which we will include a brief write-up.

Construction Status / August 15, 2017

Construction Status – Shopnobilash, Savar, Dhaka

Construction Status / August 12, 2017

Construction Status (August 2017) – The Orient, Chittagong

Construction Status / July 20, 2017

Construction Status (July, 2017) –New Haven, Chittagong

Construction Status / July 17, 2017

Construction Status (July, 2017) – Pinemont, Uttara, Dhaka

Construction Status / July 16, 2017

Construction Status (July, 2017) – Paradiso, Uttara, Dhaka

Construction Status / July 15, 2017

Construction Status (July, 2017) – Aplomb, Uttara, Dhaka

Construction Status / July 15, 2017

Construction Status (July, 2017) – Glendale, Uttara, Dhaka

Construction Status / July 15, 2017

Construction Status (July, 2017) – Dolly, Dhanmondi, Dhaka

August 15, 2017 // 11:44 am

Construction Status – Shopnobilash, Savar, Dhaka

bti-Project-Construction-Status-7

Achievement Program for the month of July, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Mobilization work 100% 100% 100%
2 Building Layout work 100% 100% 100%
3 Building Layout checking work 100% 100% 100%

Program for the month of August, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Earth work in Excavation (1st phase) 10% 10%
2 Footing work shuttering, re-bar & casting work 5% 5%

Some of the project picture

Front View

IMG_0352

Mobilization work

IMG_0350


August 15, 2017 // 12:00 am

Construction Status (August, 2017) – Haque Palace, Dhanmondi, Dhaka

Achievement in the month of July, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Wall tiles major area completed, minor area work ongoing 100% 100% 2%
2 General floor marble and tiles, major area completed 100% 100% 2%
3 Swimming pool wall and floor tiles work 100% 95% 5%
4 Stair tiles work 100% 100% 10%
5 Internal paint 1st coat 75% 25% 25%
6 Bathroom wall tiles pointing 100% 50% 50%

Program for the month of August, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Aluminium work 50% 50%
2 Swimming pool wall and floor tiles work 100% 5%
3 Pavement tiles work at basement 50% 50%
4 Internal paint 1st coat 100% 75%
5 Fitting fixing of door shutter 80% 80%
6 Internal paint 2nd coat 50% 50%
7 Bathroom wall tiles pointing 100% 50%

Some of the project pictures

Hoque Palace

Stair tiles work

Stair tiles work

Swimming pool wall and floor tiles work

Swimming pool wall and floor tiles work

Wall tiles major area completed, minor area work ongoing

Wall tiles major area completed, minor area work ongoing

Internal paint 1st coatInternal paint 1st coat

Aluminium work

Aluminium work


August 15, 2017 // 12:00 am

Construction Status ( August, 2017) – Centara Grand, Green Road, Dhaka

Achievement for the month of July, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Foundation work, Front side 100% 100% 100%
2 Mat casting, Front side 100% 100% 100%
3 1st floor roof casting, 1st phase 100% 100% 100%
4 2nd floor column casting, 1st phase 100% 100% 100%
5 Basement floor roof casting, 2nd phase 100% 100% 100%

Program for the month of August, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 GF column shuttering, re-bar  & casting work (phase-1) 100% 100%
2 GF roof slab shuttering & re-bar work (phase-1) 100% 100%
3 I-Joist driving (Phase -02) 100% 100%
4 Earth cutting (Phase -02) 50% 50%

Some of the project pictures

Front View

IMG_1877

1st floor roof casting, 1st phase

IMG_1872

Foundation work, Front side

IMG_1874

I-Joist driving (Phase -02)

IMG_1875


August 15, 2017 // 12:00 am

Construction Status ( August, 2017 ) – The Accord, Dhanmondi, Dhaka

Achievement for the month of July, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Tower-1, 2 & 3 LCC Work 100% 95% 5%
2 Tower-3, facing brick work 100% 95% 5%
3 Car parking shed fixing 100% 95% 5%
4 Tower-1 & 2 bathroom wall tiles pointing 100% 95% 5%
5 Internal paint, 1st coat T-1 & 2 100% 100% 10%
6 Pavement tiles work at T-1 100% 90% 30%
7 T-3 Verandah railing fitting 100% 100% 10%
8 Internal paint 2nd coat T-1 & 2 100% 80% 30%
9 Fitting fixing of switch socket at T-1 & 2 100% 90% 40%
10 Internal RCC Road casting 50% 50% 50%

Program for the month of  August, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Tower-1, 2 & 3 LCC Work 100% 5%
2 Tower-3, facing brick work 100% 5%
3 Car parking shed fixing 100% 5%
4 Tower-1 & 2 bathroom wall tiles pointing 100% 5%
5 Pavement tiles work at T-1 100% 10%
6 Internal paint 2nd coat T-1 & 2 100% 20%
7 Fitting fixing of switch socket at T-1 & 2 100% 10%
8 Internal RCC Road casting 100% 50%
9 Fitting fixing of main gate at T-1 & T-2 100% 100%

Some of the project pictures

Front View Tower 3

IMG_1894

Front View Tower 2

IMG_1895

Aluminium work

IMG_1892

Tower-3, facing brick work

IMG_1885

Fitting fixing of main gate at T-1

IMG_1889

Fitting fixing of main gate at  T-2

IMG_1890

Car parking shed fixing

IMG_1891

Internal RCC Road casting

IMG_1893

Main Gate Tower 2

IMG_1896

Internal paint 2nd coat T-1 & 2

IMG_3252


August 12, 2017 // 4:12 pm

Construction Status (August, 2017) – The Unity, Halishahor, Chittagong

Achievement in the month of July, 2017

SL NO Description of works Program for the month July  2017 Predicted Future Achievement up to

July -2017

Overall achievement up to this month
1 Roof top Patten stone 100% 100% 100%
2 Roof top GI wiring 100% 50% 50%
3 Type A & B verandah plaster 100% 100% 100%
4 Type CD& E verandah plaster 100% 100% 100%
5 8th floor bath & kitchen wall tiles laying 100% 100% 100%
6 2nd & 3rd floor bath room floor tiles laying 100% 100% 100%
7 1st & 2nd floor verandah railing 100% 100% 100%
8 5th & 6th floor ceiling rubbing 100% 100% 100%
9 Fire door south side plaster 100% 50% 50%

FOR THE MONTH OF August,2017

SL NO Description of works Program for the month August of  -2017 Predicted Future Achievement up to

August  -2017

1 Roof top GI wiring 50% 100%
2 8th floor bath & kitchen wall tile laying 100% 100%
3 3rd  to 8th floor verandah railing 100% 100%
4 1st to 8th floor ceiling rubbing 100% 100%
5 1st to 8th floor chipping 100% 100%
6 1st to 3rd floor mirror polish tiles laying 100% 100%
7 5th to 7th floor mirror polish tiles laying 100% 100%
8 1st to 8th fire door fitting 100% 100%
9 Out side (north) D type plaster 100% 100%
10 Substation & meter room brick work 100% 100%
11 Fire door south side plaster 50% 100%
12 Fire stair plaster with NCF 100% 100%
13 Rabbis dropping drum side plaster 100% 100%


Some Project Pictures

Front View

Front View

1st & 2nd floor verandah railing

1st & 2nd floor verandah railing

2nd & 3rd floor bath room floor tiles laying

2nd & 3rd floor bath room floor tiles laying

5th & 6th floor ceiling rubbing

5th & 6th floor ceiling rubbing

8th floor bath & kitchen wall tiles laying

8th floor bath & kitchen wall tiles laying

Fire door south side plaster

Fire door south side plaster

Roof top Patten stone

Roof top Patten stone

Type A & B verandah plaster

Type A & B verandah plaster

Type CD& E verandah plaster

Type CD& E verandah plaster


August 12, 2017 // 12:23 pm

Construction Status (August, 2017) – Ispahani Regal,South Khulshi,Chittagong

PROGRAM AND ACHIEVEMENT FOR THE MONTH OF “July-17”

Sl No. Description of Works Program
for the month of July-17
Achievement
for the month   of JUly-17
Overall achievemnet
up to this month
01 Boundary Wall Tiles Fittings (Front Side) 100% 100% 100%
02 All Void Floor Plaster With NCF 100% 100% 100%
03 All Apartment Patch Work Complete 100% 100% 100%
04 Ground Floor Sanitary Duct Wall (5″ B/W)Work 100% 100% 100%
05 Ground Floor Sanitary Duct Wall  Plaster Work 100% 100% 100%
06 Lift Wall Tiles Fitting Work Complete 100% 100% 100%
07 Ground Floor Pavement Tiles Fitting 50% 100% 100%
08 S.Bath Room PVC False Celling Fitting Complete 100% 100% 100%
09 All Bath Room Sanitary U Clamp Fitting Complete 100% 100% 100%
10 All Bath Room Cat Door Fitting Complete 100% 100% 100%
11 All Apartment Main Door Bead Fitting Complete 80% 80% 80%
12 All Apartment Internal Door Polish Work 60% 60% 60%
13 All Apartment Main Door Polish Work 80% 80% 80%
14 All Apartment Cat Door Polish Work 80% 80% 80%
15 Paint Work Final Coat 30% 30% 30%
16 All Apartment Bath Room Features Complete 50% 50% 50%

PROGRAM FOR THE MONTH OF “August-17”

Sl No. Description of Works Program
for the month of
August-17
Predicted future achievemnet up to August-17
1 Boundary Wall Tiles Fittings (South Side) 100% 100%
2 Boundary Wall Plaster Work (Front Side) 100% 100%
3 Boundary Wall Plaster Work (South Side) 100% 100%
4 Boundary Wall Berbed Wire Fitting (North & East Side) 100% 100%
5 Ground Floor Skirting Tiles Fitting Work 100% 100%
6 Ground Floor Skirting Plaster Work 100% 100%
7 Ground Floor Guard Room & Toilet Civil Work 100% 100%
8 Ground Floor Toilet Sanitary Wiring Work 100% 100%
9 Ground & 1st Floor Collumn Guard Fitting 100% 100%
10 Ground & 1st Floor 2nd Coat Paint Work 100% 100%
11 1st Floor Skirting Tiles Fitting Work 100% 100%
11 1st Floor Skirting Plaster Work 100% 100%
13 1st Floor Receiption Toilet Civil,Snitary & Tiles Work 100% 100%
14 1st Floor Receiption Toilet Sanitary Feature Work 100% 100%
15 Receiption Room Floor Tiles Fitting 100% 100%
16 Receiption Table Tiles & Marble Fitting 100% 100%
17 All Apartment Tiles Pointing Work 80% 100%
18 All Apartment Bath Room Features Fitting 100% 100%
19 All Apartment Switch Socket Fitting 50% 100%
20 All Apartment Magnative Door Stopper Fitting 100% 100%
21 All Apartment PVC Door Stopper Fitting Complete 100% 100%
22 All Kitchen Down Wash Upvc Line covered by PVC Board 100% 100%
23 All Apartment Final Coat Paint Work 100% 100%
24 Lift Wall Tiles Pointing Work 100% 100%
25 All Floor Lift Lobby 2nd Coat Paint Work 100% 100%

Some Of The Project Picture

Front Zview

Front View

All Apartment Bath Room Features Complete

All Apartment Bath Room Features Complete

All Apartment Cat Door Polish Work

All Apartment Cat Door Polish Work

All Apartment Internal Door Polish Work

All Apartment Internal Door Polish Work

All Apartment Main Door Bead Fitting Complete

All Apartment Main Door Bead Fitting Complete

All Apartment Main Door Polish Work

All Apartment Main Door Polish Work

All Bath Room Cat Door Fitting Complete

All Bath Room Cat Door Fitting Complete

All Bath Room Sanitary U Clamp Fitting Complete

All Bath Room Sanitary U Clamp Fitting Complete

Boundary Wall Tiles Fittings (Front Side)

Boundary Wall Tiles Fittings (Front Side)

Ground Floor Pavement Tiles Fitting

Ground Floor Pavement Tiles Fitting

Ground Floor Sanitary Duct Wall Plaster Work

Ground Floor Sanitary Duct Wall  Plaster Work

Ground Floor Sanitary Duct Wall (5 BW)Work

Ground Floor Sanitary Duct Wall (5 BW)Work

Lift Wall Tiles Fitting Work Complete

Lift Wall Tiles Fitting Work Complete

Paint Work Final Coat

Paint Work Final Coat

S.Bath Room PVC False Celling Fitting Complete

S.Bath Room PVC False Celling Fitting Complete


August 12, 2017 // 10:33 am

Construction Status (August, 2017 ) – Sattar Manzil,K B Abdur Sattar Rd, Rohomotgong, Chittagong

Achievement Program for the month of July, 2017

Sl No. Description of Works Program
for the month of
July-2017
Achievement of July-2017 Overall achievement up to this month
1 3rd & 4th Floor column shuttring, rod binding & casting 50% 50% 100%
2 7th Floor column shuttring, rod binding & casting 50% 50% 50%
3 7th Floor Roof Shuttring, rod binding & casting 50% 0% 0%
4 3rd & 4th Floor Roof shuttring, rod binding & casting 50% 100% 100%
5 Brick layout 1st floor 100% 1000% 100%
6 Brick layout 2nd & 3rd floor 50% 50% 100%
7 Brick layout 4th & 5th  floor 50% 50% 50%
8 Brick work 1st floor 100% 100% 100%
9 Brick work 2nd floor & 3rd floor 60% 0% 0%
10 Brick work 4th floor & 5th floor 50% 50% 50%
11 Ceiling plaster 2nd floor 100% 100% 100%
12 Ceiling plaster 3rd, 4th, 5th floor 50% 50% 50%
13 Ancillary work 1st floor 100% 50% 50%


PROGRAM FOR THE MONTH OF August/2017″

Sl No. Description of Works Program
for the month of
August/2017
Predicted
future achievement
up to August/2017
1 7th Floor Roof Shuttring, rod binding & casting 50% 50%
2 Brick work 2nd floor & 3rd floor 70% 70%
3 Ancillary work 1st floor 50% 50%
4 Ancillary work 2nd floor 70% 70%
5 Brick layout 4th & 5th floor 50% 100%
6 8th Floor Column Shuttring, rod binding & casting 50% 50%
7 5th & 6th Floor Column Shuttring, rod binding & casting 50% 100%
8 Ceiling plaster 3rd floor 50% 100%
9 Ceiling plaster 6th floor 50% 50%
10 Brick layout 6th floor 50% 50%
11 Brick work 6th floor 50% 50%
12 Door Frame fitting 1st floor 100% 100%
13 Inside wall plaster 1st floor 100% 100%
14 Electric Conduit fitting 1st floor 100% 100%
15 Box fitting (MK) 1st floor 100% 100%


Some of the project pictures

Front View

Front View

Ceiling plaster 3rd, 4th, 5th floor

Ceiling plaster 3rd, 4th, 5th floor

Ceiling plaster 2nd floor

Ceiling plaster 2nd floor

Brick work 4th floor & 5th floor

Brick work 4th floor & 5th floor

Brick work 2nd floor & 3rd floor

Brick work 2nd floor & 3rd floor

Brick work 1st floor

Brick work 1st floor

Brick layout 4th & 5th floor

Brick layout 4th & 5th  floor

Brick layout 2nd & 3rd floor

Brick layout 2nd & 3rd floor

Brick layout 1st floor

Brick layout 1st floor

Ancillary work 1st floor

Ancillary work 1st floor

7th Floor Roof Shuttring, rod binding & casting

7th Floor Roof Shuttring, rod binding & casting

7th Floor column shuttring, rod binding & casting

7th Floor column shuttring, rod binding & casting

3rd & 4th Floor Roof shuttring, rod binding & casting

3rd & 4th Floor Roof shuttring, rod binding & casting

3rd & 4th Floor column shuttring, rod binding & casting

3rd & 4th Floor column shuttring, rod binding & casting


August 12, 2017 // 12:00 am

Construction Status (August, 2017) – The Hill Crest, Dev Pahar H/S, Chittagong

Achievement for the month of July, 2017

S L No. Description of work Program for the month of july’2017 Achievement for the month of  July’ 2017 Overall achievement up to this month.
7 Fountain civil work. 70% 70% 00
1 Ground floor reception table, east west side slab extension. 50% 30% 80%
9 Main gate fitting work. 100% 100% 100%
2 Roof top bath room and BRB-Q tiles work 30% 30% 100%
3 Reception area floor tiles work. 75% 0 0
4 A3 and D4 Commode basin and cp fitting work. 100% 100% 100%
5 Sub- Main cable laying work all floor. 50% 50% 100%
8 Electric switch socket fitting 50% 50% 50%
10 Rooftop retting arrangement civil and tiles work. 100% 100% 100%
11 Vervet wire fitting in boundary wall top. 50% 50% 50%
6 Bed room and bath room door shutter fitting. all floor 20% 20% 100%
12 Wall tiles pointing work in all floor 50% 50% 50%

Program for the month of August’2017

SL Description of work Program for the month of June’2017 predicted future achievement up to june’2017
1 Ground floor reception table and east west side slab extension. 20% 100%
2 Reception area floor tiles work. 75% 75%
3 Fountain civil work. 70% 70%
4 Electric switch and socket fitting. 40% 90%
5 vervet wire fitting in boundary wall top. 50% 100%
6 Wall tiles pointing work all floor. 50% 100%
7 Floor tiles pointing work (12X12)’’ 100% 100%
8 Floor tiles pointing work (24X24)’’ 50% 50%
9 Parking grill fitting. 100% 100%
10 Parking tiles fitting work in ground floor. 100% 100%
11 Guard room and bin center civil work. 100% 100%
12 2nd coat plastic paint work all floor. 100% 100%
13 All floor sanitary cp fitting work all floor. 100% 100%
14 Wooden surface polish work. 80% 80%

Some of Project pictures

Front View

Front View

Ground floor reception table, east west side slab extension

Ground floor reception table, east west side slab extension

Main gate fitting work

Main gate fitting workRoof top bath room

Roof top bath room

BRB-Q tiles work

BRB-Q tiles work

A3 and D4 Commode basin and cp fitting work.

A3 and D4 Commode basin and cp fitting work.

Bed room and bath room door shutter fitting. all floor

Bed room and bath room door shutter fitting. all floor

Electric switch socket fitting

Electric switch socket fitting

Rooftop retting arrangement civil and tiles work.

Rooftop retting arrangement civil and tiles work.

Sub- Main cable laying work all floor.

Sub- Main cable laying work all floor.

Vervet wire fitting in boundary wall top.

Vervet wire fitting in boundary wall top.

Wall tiles pointing work in all floor

Wall tiles pointing work in all floor


August 12, 2017 // 12:00 am

Construction Status (August, 2017) – Meadowville, North Khulshi, Chittagong

Achievement for the month of July,2017

Sl No. Description of Works Program
for the month of
July – 2017
Achievement
for the month of
July – 2017
Overall achievement
up to this month
1 4th floor column casting 20% 20% 100%
2 4th floor stair casting 75% 75% 100%
3 4th floor roof beam & slab shuttering 100% 100% 100%
4 4th floor roof beam & slab rod binding 100% 100% 100%
5 4th floor roof beam & slab casting 100% 100% 100%
6 Ground floor ceiling plaster 30% 30% 100%
7 1st floor ceiling plaster 100% 50% 50%
8 1st floor brick work i/c lintel & false slab 30% 30% 30%

PROGRAM FOR THE MONTH OF “AUGUST – 2017”.

Sl No. Description of Works Program
for the month of
August- 2017
Predicted
future achievement
up to August- 2017
1 5th floor column casting 100% 100%
2 5th floor stair casting 100% 100%
3 5th floor roof beam & slab shuttering 50% 50%
4 4th floor roof beam & slab rod binding 50% 50%
5 4th floor roof beam & slab casting 50% 50%
6 1st floor ceiling plaster 50% 100%
7 2nd floor ceiling plaster 100% 100%
8 3rd floor ceiling plaster 50% 50%
9 1st floor brick work i/c lintel & false slab 30% 60%
10 2nd floor brick work i/c lintel & false slab 50% 50%
11 3rd floor brick work i/c lintel & false slab 30% 30%

Some of Project Pictures

Front View

Front View

1st floor brick work ic lintel & false slab

1st floor brick work ic lintel & false slab

1st floor ceiling plaster

1st floor ceiling plaster

4th floor column casting

4th floor column casting

4th floor roof beam & slab casting

4th floor roof beam & slab casting

4th floor roof beam & slab shuttering

4th floor roof beam & slab shuttering

4th floor stair casting

4th floor stair casting

Ground floor ceiling plaster

Ground floor ceiling plaster


August 12, 2017 // 12:00 am

Construction Status ( August, 2017) – The Prestige, Hill View HS, Chittagong

Achievement for the month of July, 2017

Sl No Description of Works Program for the month of July-2017 Achievement for the month of July2017 over all achievement up to this month
1 Kitchen counter slab complete with brick word & casting all flats 10% 00% 90%
2 LCC Work 50% 50% 80%
3 West Side Plaster 40% 20% 60%
4 C4+B4+B5 internal Plaster 40% 40% 80%
5 Electrical PVC Conduit Wiring (C4+B4+B5) 40% 80% 80%
6 Tiles work (A2+A3+A5+B2+B6+C3+C7+B3+A4) 10% 10% 60%
7 Stair Railing 30% 30% 100%
8 Ver. Railing 50% 50% 60%
9 B1+C1+C2+, B7,B8,C8 (tiles work) 30% 30% 60%
10 Marbel Fitting (A2+A3+A5+B2+B6+C3+C7+B3+A4) 20% 20% 100%
11 Sink fitting (A2+A3+A5+B2+B6+C3+C7+B3+A4) 50% 50% 100%
12 Shower Tray Fitting (A2+A3+A5+B2+B6+C3+C7+B3+A4) 80% 20% 20%
13 Electrical PVC Conduit wiring (A9, B9, C9) 20% 20% 20%
14 Cable wiring A2,A3,A4,A5,  B2,B3,B5,B6, C3,C7 80% 60% 20%
15 Bathtub fitting A2,A3,B2,B5 100% 60% 60%
16 Ceiling Plaster 9th floor 80% 50% 50%
17 Internal Wall plaster 9th floor 50% 20% 20%

Program for the month of  August,2017

Sl No Description of Works Program for the month of August, 2017 Predicted future Achievement up to of August, 2017
1 Kitchen counter slab complete with brick work& casting all flats 10% 100%
2 LCC Work 100% 100%
3 West Side Plaster 60% 100%
4 C4+B4+B5 internal Plaster 50% 90%
5 Electrical PVC Conduit Wiring (C4+B4+B5) 55% 95%
6  Wall Tiles work B1, C1,C2,A6,A7,B7,A8,B8,C8,A9,B9,C9 40% 100%
7 Ver. Railing 50% 100%
8 Floor tiles B1, C1,C2,A6,A7,B7,A8,B8,C8,A9,B9,C9 50% 100%
09 Marbel Fitting (A2+A3+A5+B2+B6+C3+C7+B3+A4) 80% 100%
10 Sink fitting (A2+A3+A5+B2+B6+C3+C7+B3+A4) 50% 100%
11 Shower Tray Fitting (A2+A3+A5+B2+B6+C3+C7+B3+A4) 80% 100%
12 Electrical PVC Conduit wiring (A9, B9, C9) 80% 100%
13 Cable wiring A2,A3,A4,A5,  B2,B3,B5,B6, C3,C7 40% 100%
14 Bathtub fitting A2,A3,B2,B5 50% 100%
15 Ceiling Plaster 9th floor 50% 100%
16 Internal Wall plaster 9th floor 80% 100%
17 Kitchen  granite fitting B1, C1,C2,A6,A7,B7,A8,B8,C8,A9,B9,C9 80% 100%
18 Boundary  wall 90% 100%


Some of the project picture

Front View

Front View

B1+C1+C2+, B7,B8,C8 (tiles work)

B1+C1+C2+, B7,B8,C8 (tiles work)

Bathtub fitting A2,A3,B2,B5

Bathtub fitting A2,A3,B2,B5

C4+B4+B5 internal Plaster

C4+B4+B5 internal Plaster

Cable wiring A2,A3,A4,A5, B2,B3,B5,B6, C3,C7

Cable wiring A2,A3,A4,A5,  B2,B3,B5,B6, C3,C7

Ceiling Plaster 9th floor

Ceiling Plaster 9th floor

Electrical PVC Conduit wiring (A9, B9, C9)

Electrical PVC Conduit wiring (A9, B9, C9)

Electrical PVC Conduit Wiring (C4+B4+B5)

Electrical PVC Conduit Wiring (C4+B4+B5)

Internal Wall plaster 9th floor

Internal Wall plaster 9th floor

Kitchen counter slab complete with brick word & casting all flats

Kitchen counter slab complete with brick word & casting all flats

LCC Work

LCC Work

Marbel Fitting (A2+A3+A5+B2+B6+C3+C7+B3+A4)

Marbel Fitting (A2+A3+A5+B2+B6+C3+C7+B3+A4)

Sink fitting (A2+A3+A5+B2+B6+C3+C7+B3+A4)

Sink fitting (A2+A3+A5+B2+B6+C3+C7+B3+A4)

Stair Railing

Stair Railing

Tiles work (A2+A3+A5+B2+B6+C3+C7+B3+A4)

Tiles work (A2+A3+A5+B2+B6+C3+C7+B3+A4)

Ver. Railing

Ver. Railing

West Side Plaster

West Side Plaster