Happy Days

Bashundhara R/A, Dhaka

Completion Date

September 2024

Status Updated

March, 2024

SL. No Name of the work Location Progress details
01 Foundation work   100% completed.
02 Super Structure work   95% Completed
03 Block Work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

90% Completed

04 Electrical conduiting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

80% Completed

 

05 Door frame fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

06 Sanitary & plumbing line work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

85% Completed

80% Completed

20% Completed

07 In side Plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

08 Electrical cable wiring work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

 20% Completed

20% Completed

20% Completed

20% Completed

100% Completed

20% Completed

20% Completed

20% Completed

09 Wall tiles work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

40% Completed

40% Completed

40% Completed

40% Completed

40% Completed

40% Completed

40% Completed

10 Common sanitary & Plumbing line work    
11 Outside plastering work   40% Completed
12 Floor tiles/Marble work    
13 L.C.C work    

 

14 Grill & Railing work    
15 Inside paint & Polishing work    
16 Switch -Socket fitting work    
17 Outside paint work    
18 Door shutter work    
19 Aluminum work    
20 Tiles Pointing work & Marble finishing work    
21 Commode – Basin fitting work and C.P fittings work    
22 Lift/Generator /Substation /Solar work    
23 Boundary wall /Ground floor development work   30% completed
24 Roof top finishing work    
25 Roof top Gardening work G.F Garden work    