Completion Date
September 2024
Status Updated
March, 2024
SL. No | Name of the work | Location | Progress details |
01 | Foundation work | 100% completed. | |
02 | Super Structure work | 95% Completed | |
03 | Block Work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top |
100% Completed
100% Completed 100% Completed 100% Completed 100% Completed 100% Completed 100% Completed 100% Completed 90% Completed |
04 | Electrical conduiting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top |
100% Completed
100% Completed 100% Completed 100% Completed 100% Completed 100% Completed 100% Completed 100% Completed 80% Completed
|
05 | Door frame fitting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 |
100% Completed
100% Completed 100% Completed 100% Completed 100% Completed 100% Completed 100% Completed 100% Completed |
06 | Sanitary & plumbing line work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
95% Completed
95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 85% Completed 80% Completed 20% Completed |
07 | In side Plastering work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 |
95% Completed
95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed |
08 | Electrical cable wiring work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 |
20% Completed
20% Completed 20% Completed 20% Completed 100% Completed 20% Completed 20% Completed 20% Completed |
09 | Wall tiles work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 |
40% Completed
40% Completed 40% Completed 40% Completed 40% Completed 40% Completed 40% Completed |
10 | Common sanitary & Plumbing line work | ||
11 | Outside plastering work | 40% Completed | |
12 | Floor tiles/Marble work | ||
13 | L.C.C work |
|
|
14 | Grill & Railing work | ||
15 | Inside paint & Polishing work | ||
16 | Switch -Socket fitting work | ||
17 | Outside paint work | ||
18 | Door shutter work | ||
19 | Aluminum work | ||
20 | Tiles Pointing work & Marble finishing work | ||
21 | Commode – Basin fitting work and C.P fittings work | ||
22 | Lift/Generator /Substation /Solar work | ||
23 | Boundary wall /Ground floor development work | 30% completed | |
24 | Roof top finishing work | ||
25 | Roof top Gardening work G.F Garden work |