Happy Days

Bashundhara R/A, Dhaka

Completion Date

September 2024

Status Updated

February, 2024

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed.  
02 Super Structure work   95%  
03 Block Work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

80% Complete

 
04 Electrical conduiting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

50% Complete

 

 
05 Door frame fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

 
06 Sanitary & plumbing line work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

85% Complete

80% Complete

10% Complete

 
07 In side Plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

 

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

90% Complete

 

 
08 Electrical cable wiring work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

 

 20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

 

 

 
09 Wall tiles work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

 

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

 

 
10 Common sanitary & Plumbing line work      
11 Outside plastering work   10% Complete  
12 Floor tiles/Marble work      
13 L.C.C work    

 

 
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode – Basin fitting work and C.P fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work   30%  
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      