March 2021 – Camelia at Kolabagan
| |
---|
Name of the work | Progress details |
Foundation work | Completed |
Super Structure work | Completed. |
Block Work | Completed |
Electrical conduting work | Completed |
Door frame fitting work | Completed |
Sanitary & plumbing line work | Completed. |
In side Plastering work | Completed |
Electrical cable wiring work | Completed. |
Wall tiles work | Completed. |
Common sanitary & Plumbing line work | Completed. |
Outside plastering work | Completed. |
Floor tiles/Marble work | Completed. |
L.C.C work | Completed. |
Grill & Railing work | Completed. |
Inside paint & Polishing work | 2nd coat Completed. final coat 5 nos flat completed. |
Switch -Socket fitting work | completed. |
Outside paint work | 1st coat Paint Completed. Final Coat on going |
Door shutter work | Completed. |
Aluminum/Glazing work | Completed. |
Tiles Pointing work & Marble finishing work | Completed |
Commode - Basin fitting work and C.P fittings work | Completed |
Lift/Generator /Substation /Solar work | Lift-95%, Generator-100%.Substation-100%.Solar-100%. |
Boundary wall /Ground floor development work | Completed. |
Roof top finishing work | Completed |
Roof top Gardening work | Completed. |