Name of the work | Progress details |
Foundation work | 100% completed |
Super Structure work | Ground floor slab 100%,1st floor 100%,2nd floor slab casting work 100% completed.3rd floor slab casting 100% complete. 4th floor slab casting 100% completed. 5th floor slab casting 100%.6th floor slab casting 100% complete. 7th floor slab casting 100% completed. 8th floor slab casting 100% complete.9th floor slab casting 100% complete.10th floor slab casting 100% complete. roof floor slab casting 100% completed. Roof floor column casting 100% completed. Roof top exercise studio top, swimming pool bottom slab & wall casting 100% completed.Swimming pool deck slab casting 100% complete |
Block Work | 1 st floor A-type 95%, B-type 95% complete.2nd floor A-type 95%, B-type 95% complete.3rd floor A-type 95%, B-type 95% complete. 4th floor A-type 90%, B-type 90% complete.5th floor A-type 95%, B-type 95%,6th floor A- type 95%, B-type 95% ,7th floor A-type 95%, B-type 95% complete. 8th floor 40% complete. 9th floor A type-90% B type-90%. 10th floorA-type 50% B-type 70% complete. |
Electrical conducting work | Electrical conducting work slab ground & 1st , 2nd, 3rd ,4th, 5 th,6th,7th,8th,9th,10th floor roof conducting complete .1st floor wall A-type 100%, B-type 100%, 2nd floor wall A-type 100%, B-type 100%, 3rd floor wall A-type 100%, B-type 100%, 4th floor A-type100%, B-type 100%, 5th floor A-type 100%, B-type 100% ,6th floor A-type 100%,B-type 100%complete. 7th A-type-100% B type-100%. 8 th floor 40%.9th floor A type-80%, B type-80%.10th floor A-type 50%,B-Type 80% |
Door frame fitting work | 1 st floor A-type 90%, B-type 90% complete. 2th floor A-type 90% B-type 90%, 3rd floor A-type 90%, B-type 90%,4th floor A-type 90% B-type 90%,5th floor A-type 90%, B-type 90% complete.6th floor A-type 90%, B-type 90%.7th floor A-type 90%,B-type 90% complete |
Sanitary & plumbing line work | 3rd floor A-type 90%,B-type 90%.5th floor A-type 80%,B-type 80%.7th floor A-type 50%,B-type 50% complete |
In side Plastering work | In side Plastering work basement-1&2 ceiling 90% wall 90% complete. 1st,2nd,3rd,4th,5th,6th,7th,8th,9th floor ceiling plaster 100% complete.1st floor wall A-type 80%, B-type 80%,2nd floor A-type 90% B-type 90%, 3rd floor A-type 90%, B-type 90%,4th floor A-type 90%,B-type 90% complete.5th floor A-type-90% B-type-90%.6th floor A-type 80% B-type 80%. 7th floor A-type 80%, B-type 80% complete |
Electrical cable wiring work | Electrical cable wiring work basement-1&2 floor 90% completed |
Wall tiles work | |
Common sanitary & Plumbing line work | |
Outside plastering work | |
Floor tiles/Marble work | |
L.C.C work | |
Grill & Railing work | |
Inside paint & Polishing work | |
Switch -Socket fitting work | |
Outside paint work | |
Door shutter work | |
Aluminum/Glazing work | |
Tiles Pointing work & Marble finishing work | |
Commode - Basin fitting work and C.P fittings work | |
Lift/Generator /Substation /Solar work | |
Boundary wall /Ground floor development work | |
Roof top finishing work | |
Roof top Gardening work | |