March 2021 – Royal Oaks at Bashundhara R/A

Name of the work | Progress details |
Foundation work | 100% complete. |
Super Structure work | 97% complete. |
Block Work | 1st-9th floor-100%, 10th-12th floor-70% complete. |
Electrical conduting work | 1st-10th floors-80%. |
Door frame fitting work | 90% complete. |
Sanitary & plumbing line work | 1st-9th floor-100% complete, others in progress. |
In side Plastering work | 1st-9th floor-100% complete, others in progress. |
Electrical cable wiring work | 25% complete. |
Wall tiles work | 3rd- 8th floors-60% complete. |
Common sanitary & Plumbing line work | Under progress. |
Outside plastering work | N/A |
Floor tiles/Marble work | N/A |
L.C.C work | N/A |
Grill & Railing work | N/A |
Inside paint & Polishing work | N/A |
Switch -Socket fitting work | N/A |
Outside paint work | N/A |
Door shutter work | Main entries under procurement. |
Aluminum/Glazing work | N/A |
Tiles Pointing work & Marble finishing work | N/A |
Commode - Basin fitting work and C.P fittings work | N/A |
Lift/Generator /Substation /Solar work | N/A |
Boundary wall /Ground floor development work | N/A |
Roof top finishing work | N/A |
Roof top Gardening work | N/A |