Construction Status (April, 2018) – Silver Dale, Uttara, Dhaka

Construction Status

Serial No. Name of work Achievement Up to month March, 2018 Program  Up to month April, 2018
Target Achievement Target  
01 9th fl. Clmn rebar & form works 100% 100%
02 9th fl. Clmn casting works 100% 100%
03 Door frame fitting (1st,2nd & 3rd ) 100% 100%
04 False slab, lintel form, rebar & casting (2nd Fl.) 100% 100%
05 Inside plaster work up to 2nd fl. 100% 100%
06 Elec. Conduiting works (2nd,3rd,4th ) 100% 100%
07 Ceiling plaster up to 7th floor 100% 100%
08 Block work completed (4th,5th& 6th ) 100% 100%
09 Roof lift room top & bottom completed 100%
10 OHWT top & bottom completed 100%
11 Roof C. Hall slab casting completed. 100%
12 Door frame fitting (4th,5th Fl) 100%
13 False slab & lintel completed(3rd,4th & 5th Fl) 100%
14 Elec. Conduiting (5th,6th Fl) 100%
15 Inside Plaster (3rd, 4th ) 100%
16 Ceiling Plaster (8th Fl) 100%
17 Block work 7th & 8th floor 50%
19 Internal PPR works (1st , 2nd & 3rd ) 100%


Some of the project picture