Construction Status (April, 2018) – Adelina, Bashundhara, Dhaka

Construction Status

Serial No. Name of work Achievement for the month of March Program  for the month of April
Target Achievement Target  
01 Kitchen & Bath floor tiles 100% 80% 100%
02 Lcc works at root top 100% 100%
03 Marble & Granite at counter top 100% 80% 100%
04 Roof top water line 70% 0% 70%
05 Stair tiles fittings works 40% 0% 40%
06 Boundary wall civil works 100% 0% 100%
07 Grill fittings works 100% 100%
08 Verandah railing fittings works 100% 100%
09 Bath room floor tiles works 50%
10 Roof tof floor tiles works 50%
11 Paint works ( Rubbing & Sealer apply ) 25%