Construction Status (April, 2018) – Pinemont, UTTARA, DHAKA

Construction Status

Serial No. Name of work Achievement Up to month March, 2018 Program  Up to month April, 2018
Target Achievement Target  
01 8th floor roof slab shuttering & Rebar works 100% 100%
02 8th floor roof slab casting 100% 100%
03 Roof top column rebar & shutter works 100% 100%
04 Roof top column casting 100% 100%
05 Ceiling Plaster complete (5th floor) 100% 100%
06 Brick work complete 4th floor 100% 100%
07 Door frame fitting up to 1st floor 100% 20% 100%
08 False slab & lintel up to 2nd floor 50% 50% 100%
09 Lift M. room bottom slab shutter 100%
10 Lift M. room  slab rebar & casting 100%
11 OHWT bottom slab shutter work 100%
12 OHWT bottom slab rebar & casting works 100%
13 Community room slab shutter works 100%
14 Community room slab rebar works 50%
15 Ceiling plaster complete (7th floor) 100%
16 Block work complete (4th floor) 100%
17 Block work (5th floor) 75%
19 Door frame fitting 2nd floor 50%