Construction Status ( January, 2018) – Atlantis, Gulshan, Dhaka

Achievement Program for the month of December, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Inside Plaster at all floor 90% 90% 5%
2 Outside plaster at all floor 65% 65% 20%
3 Sanitary internal wiring at all floor 100% 100% 5%
4 Wall tiles at all floor 80% 80% 15%
5 Floor Tiles/ Marble work at all floor 25% 25% 25%
6 LCC preparation 100% 100% 75%
7 Cable wiring at all floor 100% 100% 30%
8 UPVC vertical wiring work at all floor 50% 50% 15%
9 Window grill fitting at all floor 25% 25% 20%

Program for the month of January, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Inside Plaster at all floor 95% 5%
2 Outside plaster at all floor 75% 10%
3 Wall tiles at all floor 83% 3%
4 Floor Tiles/ Marble work at all floor 35% 10%
5 LCC Work 100% 100%
6 UPVC vertical wiring work at all floor 90% 40%
7 Window grill fitting at all floor 50% 25%
8 Outside Rustic tiles at all floor 60% 60%
9 Internal Gasline wiring work at all floor 50% 50%