Construction Status (February, 2018) – Bonaire, Lalmatia, Dhaka

Achievement Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Floor tiles 100% 100% 5%
2 Boundary walls 100% 95% 5%
3 LCC works 100% 100% 5%
4 GF civil works 100% 80% 20%
5 Facing bricks 100% 100% 5%
6 Aluminium works 20% 0% 0%
8 Stair and Roof top tiles 100% 100% 45%
9 Parking tiles 50% 50 50
10 GF sanitary lines 50% 50 50
11 Substation cable wiring 80% 80 80

Program for the month of February, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Boundary walls 100% 5%
2 LCC works 100% 5%
3 GF civil works 100% 20%
4 Aluminium works 20% 20%
5 Stair and Roof top tiles 100% 45%
6 Parking tiles 50% 50%
7 GF sanitary lines 50% 50%
8 Substation cable wiring 80% 80%
9 Paint-Surface preparation/Internal 100% 100%
        1st coat 80% 80%
10 External paint-Surface preparation 50% 50%
11 Stair railing 70% 70%

Some of the project picture