Construction Status (April, 2018) – Bonaire, Lalmatia, Dhaka

Construction Status

Serial no. Name of work Up to March’18 Program  up to April’18
Target,% Achievement,% Target,%  
01 Aluminium works 40 40 80
02 Paint surface preparation/Internal 50 50 100
1st coat 80 80 100
04 Paint surface preparation/External 100 60 100
1st coat 50 50 80
05 Stair Railing 100 50 100
06 Enamel paint-1st coat 30
08 Wall tiles’ pointing 40
09 Polish work on wooden surfaces 10