Construction Status (February, 2018) – bti Landmark, Gulshan Avenue, Dhaka

Achievement Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Sanitary GI/PPR wiring work at roof top area 100% 100% 15%
2 Wall Tiles work at all floor ( Except GF) 100% 100% 1%
3 Floor Tiles work at all floor 97% 97% 2%
4 Fair Face finishing work 95% 95% 5%
5 Lift pit construction work 95% 95% 5%
6 Glass curtain framing wall work 70% 70% 20%
7 Steel Structure work 30% 15% 0%
8 Boundary wall construction work 95% 95% 5%
9 Roof top Garden construction work 100% 100% 5%
10 LCC work 100% 100% 10%
11 Fire Hydrent & Water Sprinkler work 97% 97% 2%
12 Iinternal Paint (Sealer & Putty) at all floor 95% 95% 5%
13 Iinternal Paint (1st Coat) at all floor 50% 50% 20%
14 Iinternal Paint (2nd Coat) at all floor 10% 10% 10%
15 AC ducting work 60% 60% 15%
16 BBT room door fitting at all floor 100% 100% 100%
17 Lift lobby Marble fitting work at all floor 50% 50% 50%

Program for the month of February, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Wall Tiles work at all floor (GF) 85% 85%
2 Floor Tiles work at all floor 98% 1%
3 Fair Face finishing work 100% 5%
4 Lift pit construction work 100% 5%
5 Glass curtain framing wall work 90% 20%
6 Steel Structure work 30% 15%
7 Boundary wall construction work 100% 5%
8 Fire Hydrent & Water Sprinkler work 98% 1%
9 Iinternal Paint (Sealer & Putty) at all floor 98% 3%
10 Iinternal Paint (1st Coat) at all floor 80% 30%
11 Iinternal Paint (2nd Coat) at all floor 25% 15%
12 AC ducting work 100% 40%
13 BBT work 25% 25%
14 Lift lobby Marble fitting work at all floor 75% 25%
15 Water body construction work 50% 50%