Construction Status (April, 2018) – bti Landmark, Gulshan Avenue, Dhaka

Construction Status

Serial No. Name of work Achievement Up to month March, 2018 Program  Up to month April, 2018
Target Achievement Target  
01 Wall tiles works at G.F 100% 95% 100%
02 Fl. Tiles works at all floor 100% 95% 100%
03 Fair face finishing works 100% 100%
04 Lift pit construction works 100% 100%
05 Curtain Glass framing works 100% 100%
06 Steel structure works 60% 40% 60%
07 Boundary wall construction works 100% 100%
08 Fire Hydrant & water sprinkler works 100% 100%
09 Int. Paint(Sealer & Putty) at all fl. 100% 100%
10 Int. Paint (1st coat) at all floor 100% 90% 100%
11 Int. Paint (2nd coat) at all floor 50% 40% 50%
12 AC ducting works 100% 80% 90%
13 Bush Bar Tank (BBT) works 80% 80% 100%
14 Lift lobby marble fitting works all Fl. 95% 95% 100%
15 Water Body const. works 100% 90% 100%
South side Ramp Construction works 100% 100%
16 Fire Brigade line connection works 50%
17 Int. Ceiling paint (Sealer & Putty)all basement 80%
18 Int. Ceiling paint (1st ct)all basement 80%
19 Int. paint (1st coat)all Fl 100%
20 Int. paint (2nd coat)all Fl 50%
21 Lift lobby marble finishing (1st Cut) 100%
22 North side ramp construction works 100%
23 Lift lobby false ceiling works 20%