Construction Status (February, 2018) – CHHAYABITHI, Uttara, Dhaka

Achievement Program for the month of January, 2018

SL  NO DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 Overhead Water Tank, T-1 & 2 50% 50% 50%
2 Roof Parapet wall 10% 10% 10%
3 Septic tank 66% 66% 33%
4 Brick work at 2nd up to 4th floor, T-1 & 2 100% 100% 50%
5 Ceiling plaster 7th floor, T-1 & 2 100% 100% 100%
6 Wall plaster Tower-1 30% 30% 10%
7 Wall plaster Tower-2 30% 30% 10%


Program for the month of February, 2018

SL  NO DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 Overhead Water Tank, T-1 & 2 100% 50%
2 Roof Parapet wall 50% 40%
3 Septic tank 66% 33%
3 Brick work at 5th floor, T-1 & 2 50% 50%
4 Ceiling plaster 8th floor, T-1 & 2 100% 100%
5 Wall plaster Tower-1 40% 10%
6 Wall plaster Tower-2 40% 10%
7 Ver railing 10% 10%