Construction Status (May, 2018) – Comity, Panchlaish, Chittagong

                                                                              Construction Status

Serial No. Name of work Achievement for the month of April-2018 Program  for the month of May-2018
Target Achievement Target  
01 Ver-2 Railing Bottom Plaster 1st to 8th floor. 100% 100%
02 Ver-2 Sliding door thai bit making 1st to 8th floor. 100% 100%
03 All ver tiles bit plaster work. 100% 100%
04 Kitchen worktop  bottom plaster 1st to 8th floor. 100% 100%
05  All bath room tiles top civil patch work 1st to 8th floor. 100% 100%
06 All bath room cabinet marbel fitting 1st to 8th floor. 100% 100%
07 All bath & All kitchen cabinet wall tiles fitting. 100% 100%
08 Lift wall tiles fitting 100% 100%
09 Roof top tiles work. 100% 100%
10 Outside master coat paint 1st coat 100% 100%
11 Internal paint work all floor.(1st coat 100% & 2nd coat 100%). 100% 50% 50%
12 G.F low level sanitary pipe laying. 100% 50% 50%
13 Lift installation work . 50% 50% 50%
14 Main door shutter fitting. 100% 100%
15 Internal flush door shutter fitting. 50% 50% 50%
16 G.F development work. 30% 30% 70%
17 Void & open terrace Development work, 100%
18 Building peripheri Apron area casting, 100%
19 Boundary wall copping & inside wall plaster, 100%
20 Driver & caretaker room macking, 100%
21 Civil patch work 5th to 8th floor, 100%
22 Roof top development work, 100%
23 Tiles patch work 4th to 8th floor, 100%
24 Wall tiles pointing work 1st to 8th floor, 100%
25 Floor tiles pointing work 5th to 8th floor, 100%
26 Stair railing fitting, 100%
27 GF pavement tiles fitting, 100%
28 Sanitary wire fitting 5th to 8th floor, 100%
29 GF sanitary High level Wiring, 100%
30 Thai aluminium work, 100%