Construction Status ( February, 2018) – Comity, Panchlaish, Chittagong

                                                         Program for the month of  January 2017

SL

NO.

Description of Work. Program for the month January ­­2018 Achivement for the month of January 2018 Overall Achivement up to month.
1 Boundary wall plaster. 100% 100% 100%
2 Sub-station & Meter room Brick Wall. 100% 100% 100%
3 Sub-station & Meter room Plaster work both side. 100% 100% 100%
4 Verandah inside plaster.(all floor) 100% 100% 100%
5 Verandah -1.2.3 floor tiles up to 4th floor. 100% 100% 100%
6 Bath-1.2.3 room floor tile.(2nd & 3rd floor.) 100% 100% 100%
7 Floor pipe laying ( 2nd to 5th floor.) 100% 100% 100%
8 Kitchen steel sink fitting.floor. 100% 100% 100%

 

9 Kitchen granite fitting.2nd to 5th floor. 100% 100% 100%
10 Sanitary vertical UPVC line leak test. 100% 100%
11 Bath room 4” UPVC connection. (commod waste line, kitchen Down wash line). 100% 100% 100%
12 Common space Grill fitting.5th to 8th floor. 100% 100% 100%

                                                         Program for the month of  February 2018

SL

NO.

Description of Work Achivement for the month of Feb 2018 Overall Achivement
1 Boundary wall inside plaster. 80% 100%
2 Boundary wall Safety grill & side fitting. 100% 100%
3 Dining room south pot planter area cc with ncf. 100% 100%
4 Bed -1&2 window bit macking 1st to 8th floor. 100% 100%
5 Machine room floor plaster with ncf. 100% 100%
6 Outside safety m.s pipe opening. 100% 100%
7 Verandah -1.2.3 floor tiles 4th  to 8th floor. 100% 100%
8 Bath-1.2.3  floor tiles 4th to 6th floor. 100% 100%
9 Ver raling fitting up to 8th floor. 100% 100%
10 Community bath sanitary pipe laying. 100% 100%
11 Roof top water distribution line installation. 100% 100%
12 Kitchen work top granite fitting 6th to 8th floor. 100% 100%
13 South side low level sanitary floor drain. 100% 100%