Construction Status (April, 2018) – Pine Ridge, Bashundhara, Dhaka

Construction Status

Serial No. Name of work Achievement for the month of March Program  for the month of April
Target Achievement Target  
01 G.Floor roof casting 100% 100%
02 1st Floor column casting 100% 100%
03 1st Floor roof  shuttering & foam works 100% 90% 100%
04 1st Floor roof casting 100%
05 2nd  Floor column casting 100%
06 2nd Floor roof  shuttering & foam works 100%