Construction Status (April, 2018) – Shopnobilash,Nabinagar, Savar

Construction Status

Serial No. Name of work Achievement up to  March 2018 Program  Up to  April 2018
Target Achievement Target
01  

Earth work in Excavation (2nd phase)

 

70% 70% 75%
02  

Footing work shuttering, re-bar & casting work (2nd  Phase)

 

30% 30% 50%
03  

Mat Casting (1st phase)

 

100% 100%
04  

Column shuttering & Rebar work (1st Phase)

 

70% 70% 80%
05  

Column Casting (1st Phase)

 

70% 70% 80%
06  

Retaining wall Shuttering & Re-bar work (1st phase)

 

30% 30% 50%
07 Retaining wall catsing (1st phase)

 

30% 30% 50%