Construction Status (March, 2018 – Dolly, Dhanmondi, Dhaka

Achievement Program for the month of February, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 RCC works-OHT 100% 100% 50%
2 Roof top parapet works 100% 100% 40%
3 3rd, 4th, 5th floor internal plaster 100% 100% 20%
4 6th, 7th, 8th floor ancilary works 100% 100% 40%
5 4th, 5th, 6th floor Electrical conduiting 100% 100% 20%
6 Sanitary, plumbing wiring-1st, 2nd floor 100% 50% 50%
7 1st up to 6th, 7th floor Door frame setting 100% 100% 100%
8 !st floor wall tiles 50% 0% 0%
9 Roof top Lift machine room 100% 100%

Program for the month of March, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 RCC works-OHT 100% 50%
2 Roof top parapet works 100% 40%
3 6th, 7th floor internal plaster 100% 100%
4 9th floor ancilary works 100% 100%
5  6th, 7th, 8th, 9th floor Electrical conduiting 100% 100%
6 Sanitary, plumbing wiring-1st, 2nd floor 100% 50%
7 8th, 9th floor Door frame setting 100% 100%
8 !st floor wall tiles 100% 100%

Some of the project picture