Construction Status (April, 2018) – Armitage, Banani, Dhaka

Construction Status

Serial No. Name of work Achievement up to March 2018 Program  up to April 2018
Target Achievement Target
01 Outside Plaster work 40% 40% 70%
02 Kitchen & Bathroom Wall tiles fitting work(All Floor) 45% 45% 60%
03 Sanitary Internal Wiring work 90% 90% 95%
04 Sample Electric Cable wiring 100% 100%
05 Electric Cable wiring of All Floor 15%
06 Window Grill fitting all floor 15% 15% 50%
07 Special Plaster for water barrier 15% 15% 30%
08 Ver. MS Railing 20%
09 Floor tiles fitting at all floor 20%
10 Outside Rustic tiles fitting 40%
11 L.C.C Work 50%
12 Outside Design groove Plaster 30%