Construction Status (February, 2018) – Centara Grand, Green Road, Dhaka

Achievement Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 2nd floor roof slab casting, Phase-1 100% 100% 50%
2 3rd floor column casting, Phase-1 100% 100% 100%
3 Earth cutting, Phase-2 100% 100% 5%
4 Foundation casting-Phase-2 100% 100% 100%
5 Retaining wall casting, Phase-2 100% 20% 20%
6 Basement column casting, Phase-2 100% 50% 50%
7 Basement Roof casting 100% 0% 0%

Program for the month of February, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Basement Column casting Phase-2 100% 50%
2 Retaining wall casting Phase-2 100% 80%
3 Under Ground Water Reservoir casting, Phase-2 100% 100%
4 GF slab casting, Phase-2 100% 100%
5 GF column casting, Phase-2 100% 100%