Construction Status (April, 2018) – LAKE PANORAMA,UTTARA, DHAKA

Construction Status

Serial No. Name of work Achievement Up to month March, 2018 Program  Up to month April, 2018
Target Achievement Target  
01 Sanitary Internal wiring at all floor 100% 60% 100%
02 Electrical conduit works up to 8th floor 100% 100%
03 Electrical conduit works up to 9th floor 100%
04 Door frame fitting up to 7th floor 100% 100%
05 Door frame fitting up to 8th floor 100%
06 Internal wall plaster completed up to 5th floor 100% 100%
07 Internal wall Plaster completed up to 8th floor 100%
08 Outside A/C drain line conduiting 100% 70% 100%
09 Wall tiles works (Bath & Kitchen) 20% 0% 20%
10 Outside Plaster (West side) 30% 30% 100%
11

 

All verandah drop wall & railing casting 40% 40% 100%