Construction Status (February, 2018) – The Orient, Chittagong

Achievement for the month of January, 2017

 

SL

 

Description of Works

Program for the month ofJanuary -2018 Achievement  for the month of January 2018 Over all achievement up to this month
1 Slab & beam shuttering work at 5th floor slab. 100%      100%     100%
2 Slab & beam reinforcement work at 5th floor slab. 100% 100% 100%
3 Slab casting work at 5th floor slab. 100% 100% 100%
4 Column casting work at 5th floor slab. 100% 100% 100%
5 Slab & beam shuttering work at 6th floor slab. 100% 100% 100%
6 Brick work up to 4’-6” height at 1st floor & layout complete & brick work start at 2nd floor. 100% 100% 100%
7 Electric P.V.C conduit pipe work at 5th floor slab. 100% 100% 100%
8 Ceiling plaster at 1st floor 100% 100% 100%

                                           Predicted future achievement up to month of February -2018

 

SL

 

Description of Works

Program for the month of

February -2018

Predicted future achievement up to month of February -2018
1 Slab & beam reinforcement work at 6th floor slab.         100%   100%
2 Slab casting work at 6th floor slab.         100%   100%
3 Column casting work at 6th floor slab.         100%   100%
4 Slab & beam shuttering work at 7th floor slab.         100%         100%
5 Slab & beam reinforcement work at 7th floor slab.         100%         100%
6 Slab casting work at 7th floor slab.         100%         100%
7 Brick work up to 7’-0” height at 1st floor.         100%         100%
8 Brick work up to 7’-0” height at 2st floor.         100%         100%
9 Brick work layout at 3rd floor.         100%         100%
10 Ceiling plaster work at 1stfloor.         100%         100%
11 Ceiling plaster work at 2ndfloor.         100%         100%
12 Electric P.V.C conduit pipe work at 6th floor slab.         100%         100%
13 Electric P.V.C conduit pipe work at 7th floor slab.         100%         100%1