Construction Status (May, 2018) – The Orient, Chittagong

                                                                                         Construction Status

Serial No. Name of work Achievement for the month of April -2018 Program  for the month of May-2018
Target Achievement Target  
01 Slab & beam shuttering work at 8th  floor slab 100% 100%
02 Slab & beam reinforcement work at 8th  floor slab 100% 100%
03 Slab casting work at 8th  floor slab 100% 100%
04 Column casting work at 8th  floor slab 100% 50%
05 Brick work up to 7′-0″ height at 4th  floor   100% 50%
06 Brick work layout at 5th  floor 100% 100%
07 Brick work up to 7′-0″ height at 5th  floor 100% 50%
08 Ceiling plaster work at 4th  floor 100% 100%
09 Ceiling plaster work at 5th  floor 100% 100%
10 Electric P.V.C conduit pipe work at 8th floor 100% 100%
11 Column casting work at 8th  floor slab   50%
12 Slab & beam shuttering work at 9th  floor slab 100%
13 Slab & beam reinforcement work at 9th  floor slab 100%
14 Slab casting work at 9th floor slab 100%
15 Brick work up to 7′-0″ height at 4th  floor 50%
16 Brick work layout at 6th  floor 100%
17 Brick work up to 7′-0″ height at 5th  floor 50%
18 Ceiling plaster work at 6th  floor 100%
19 Electric P.V.C conduit pipe work at 8th floor 100%
20 Lintel and fals slab work 1st fl  &  2nd fl. 100%
21 Brick work up to 7′-0″ height at 6th  floor 50%
22