Construction Status (April, 2018) – Glendale, Uttara, Dhaka

Construction Status

Serial No. Name of work Achievement Up to month March, 2018 Program  Up to month April, 2018
Target Achievement Target  
01 Window grill work s 100% 100%
02 Verandah railing works 100% 100%
03 Stair railing works Nil Nil 100%
04 Paving tiles works 100% 90% 100%
05 Stair tiles works 100% 90% 100%
06 Thai Aluminum 40% 40% 80%
07 1st coat paint 40% 30% 70%
08 Roof top G.I works 100% 100%
09 Main gate fitting 00% 00% 100%
10 Sub-Station , Generator room Grill fixing 100% 100%
11 Roof top door fitting 100%
12 G.F RCC line 50%
13 G.F guard room 100%
14 All marble molding 100%
15 All kitchen granite fitting 100%
16 Outside paint works 30%
17 1st floor safety sliding 100%