Construction Status (March, 2018) – Haque Palace, Dhanmondi, Dhaka

Achievement Program for the month of February, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Aluminium works 100% 100% 5%
2 Electrical switch sockets 100% 90% 10%
3 Internal paint-2nd coat 100% 100% 20%
Luxary silk-1st coat 30% 30% 30%
4 External paint,1st coat 70% 60% 15%
5 Boundary civil works,Front 70% 70% 20%
6 Reception counter 75% 75% 50%
7 BTI logo 90% 60% 60%
8 Fire alarm, CCTV etc 100% 50% 50%
9 Roof top sanitary, garden etc 75%
10 Door shutter setting 80% 100% 30%
11 Sanitary GI pipe wiring 100% 100% 60%
12 Electrical sub main cable wiring 90% 90% 90%
13 General floor Marble finish 10% 10% 10%

Program for the month of March, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
2 Electrical switch sockets, Brackets, Spot lights 100% 10%
3 Internal paint-2nd coat 100% 20%
Luxary silk-1st coat 50% 20%
4 External paint,1st coat 90% 20%
5 Boundary civil works,Front 70% 20%
6 Reception counter 100% 25%
7 BTI logo 90% 30%
8 Fire alarm, CCTV etc 100% 40%
9 Roof top sanitary, garden etc 75% 25%
10 General floor Marble finish 30% 20%
11 Indoor play area- Tiles work 100% 100%
12 Fountain tiles 100% 100%
10 Door shutter setting 80% 10%