March 2021 – Palacio at Bashundhara, Dhaka
| |
---|
Name of work | Progress details |
Foundation work | 100% complete. |
Super Structure work | 100% complete. |
Block Work | 100% complete. |
Electrical conduting work | 100% complete |
Door frame fitting work | 100% complete. |
Sanitary & plumbing line work | 100% complete. |
In side Plastering work | 100% complete. |
Electrical cable wiring work | 100% complete. |
Wall tiles work | 100% complete. |
Common sanitary & Plumbing line work | 100% complete. |
Outside plastering work | 100% complete. |
Floor tiles/Marble work | 100% complete. |
L.C.C work | 100% complete. |
Grill & Railing work | 100% complete. |
Inside paint & Polishing work | 100% Complete. |
Switch -Socket fitting work | 100% complete. |
Outside paint work | 100% Complete. |
Door shutter work | 100% complete. |
Aluminum/Glazing work | 100% complete. |
Tiles Pointing work & Marble finishing work | 100% complete. |
Commode - Basin fitting work and C.P fittings work | 100% complete. |
Boundary wall /Ground floor development work | 100% complete. |
Roof top finishing work | 9100 % complete. |
Roof top Gardening work | 100% Complete. |
Out side Rustic tiles work | 100% complete. Ready to hand over. |
| |