Construction Status (February, 2018) – New Haven (Panchlaish),Chittagong

ACHIEVEMENT FOR THE MONTH OF “January -2017”

SL. NO. Description of Works Program
for the month of January    – 2017
Achievement
for the month of January  – 2017
Overall achievement
up to this month
1 Ground  floor roof casting(east) 100% 100% 100%
2 GF lift core casting 100% 100% 100%
3 Pile cap casting (west) 30% 30% 30%
4 GF Column Steel jacket (East) 50% 50% 100%
5 Column casting(GF East site) 50% 50% 100%
6 Earth Excavation (West ) 60% 60% 80%
7 pile head breaking(west) 60% 60% 80%

Program for the month of February, 2018

Description of Works Program
for the month of January    -2018
Predicted
future achievement
up to January   -2018
1 1st floor roof casting(east) 100% 100%
2 1st floor lift core casting 80% 80%
3 Pile cap casting (west) 50% 80%
4 1st floor stair casting  (East) 100% 100%
5 Column casting1st floor (East site) 100% 100%
6 Earth Excavation (West ) 10% 90%
7 pile head breaking(west ) 10% 90%