Construction Status (May, 2018) – New Haven (Panchlaish),Chittagong

                                                                       Construction Status

Serial No. Name of work Achievement for the month of April-2018 Program  for the month of May-2018
Target Achievement Target  
01 Mat casting (West site) 50%       50%
02 Pile cap casting (west) 20% 20%
03 Retaining wall casting (west) 60% 60%
04 Earth Excavation (West ) 10% 10%
05 pile head breaking(west) 10% 10%
06 Basement Column casting (West) 100% 100%
07 Basement Roof casting (west) 100% 100%
08 Bolli work (north-west) 100% 100%
09 Ramp ceiling plaster work 100% 100%
10 Stair casting (west) 100% 100%
11 GF column jacketing(west) 100%
12 GF Column casting (West) 100%
13 GF Roof casting (west) 100%
14 Retaining wall plaster  (north-west) 100%
15 Backfilling   work(west) 100%
16 GF Stair casting (west) 100%