Construction Status (April, 2018) – Good Fortune, Uttara, Dhaka

Construction Status

Serial No. Name of work Achievement Up to month March, 2018 Program  Up to month April, 2018
Target Achievement Target  
01 Internal Paint (2nd Coat) 100% 100%
02 Internal Paint (Final Coat) 50% 50% 100%
03 Outside Paint Work (Putty) 100% 100%
04 Front Area tiles work 100% 100%
05 Sanitary ware fitting (all Flats) 100% 100%
06 G.F False ceiling 80% 80% 100%
07 Visit for observation and rectification 60% 60% 100%
08

 

Floor tiles pointing 100% 100%
09 Logo fitting 100% 100%
10 C.P fitting 100% 100%
11 Outside Paint works (Final) 25% 25% 100%
12 Lift wall tiles fitting 100%
13 Lift Installation 100%
14 Generator Installation 100%
15 1st floor casting works 100%
16 Lift wall tiles pointing 100%
17 Facing brick pointing 100%
18 Boundary fiber shed fixing 100%
19 Door shutter polish works 100%