Construction Status (April, 2018) – Paradiso, Uttara, Dhaka

Construction Status

Serial No. Name of work Achievement Up to month March, 2018 Program  Up to month April, 2018
Target Achievement Target  
01 Int. paint works at all fl(sealer Putty) 100% 100%
02 Internal door shutter fitting at all fl. 80% 80% 100%
03 Int. paint works at all floor (1st coat) 50% 50% 80%
04 Windows thai section fittings 80% 80% 100%
05 G.F. civil works 75% 75% 100%
06 G.F gardening works 75% 75% 90%
07 Outside paint works(Sealer & Putty) 100% 100%
08 G.F. pavement tiles works 50% 50% 80%
09 Sub-station HT laying and Boundary making 100% 100%
10 Window grill paint works (1st coat) 50% 50% 100%
11 Lift lobby tiles works at all floor 100% 100%
12 Outside paint works 1st coat 30%
13 Titas gas riser works 100%
14 Main gate fitting & 1st coat paint 100%
15 G.F. water pump fitting 100%
16 Cat door shutter fitting in bath room 100%
17 Verandah soccer light fitting 50%