Construction Status (February, 2018) – Paradiso, Uttara, Dhaka

Achievement Program for the month of January, 2018

SL NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 Stair tiles at all floor 100% 100% 50%
2 Sanitary RCC line work 75% 75% 25%
3 Reception area construction work 75% 75% 25%
4 Internal Paint work (Rubbing) 100% 100% 10%
5 Roof Top Patent stone & tiles work 100% 100% 50%
6 Outside Duct Louver work 100% 100% 50%
7 GF deiver waiting, Caretaker room construction work 100% 100% 50%
8 Outside Paint work (Rubbing) 100% 100% 100%
9 Internal Paint work at all Floor (Sealer & Putty) 25% 25% 25%
10 Sub-main cable wiring work 100% 100% 100%
11 Sub-station & Generator room door fitting work 100% 100% 100%
12 Internal door shutter fitting work at all floor 25% 25% 25%
13 GF Patent stone casting work 50% 50% 50%
14 Roof top front design MS work 100% 100% 100%
15 GF Cable tray fitting and cable wiring work 100% 100% 100%
16 GF 4″ UPVC pipe wiring work 100% 100% 100%
17 Lift lobby tiles work at all floor 50% 50% 50%

Program for the month of February, 2018

SL. NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 Sanitary RCC line work 100% 25%
2 Reception area construction work 100% 25%
3 Internal Paint work at all Floor (Sealer & Putty) 50% 25%
4 Internal door shutter fitting work at all floor 50% 25%
5 GF Patent stone casting work 100% 50%
6 Internal Paint work at all Floor (First cost) 20% 20%
7 Windows Thai Section fittings 30% 30%
8 GF Civil work work 50% 50%
9 GF Gardening 50% 50%
10 Lift lobby tiles work at all floor 75% 25%