Construction Status (February, 2018) – Shopno Chura, Diabari, Uttara, Dhaka

Achievement Program for the month of January, 2018

SL NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRESS UPTO THIS MONTH PROGRESS IN THIS MONTH
1 2nd floor roof re-bar & Shuttering work (T-1) 100% 100% 15%
2 2nd floor roof slab casting work (T-1) 100% 100% 100%
3 3rd floor column shuttering-rebar work (T-1) 100% 100% 100%
4 3rd floor column casting work (T-1) 100% 100% 100%
5 3rd floor column shuttering-rebar work (T-2) 100% 100% 100%
6 3rd floor column casting work (T-2) 100% 100% 100%
7 3rd floor roof slab shuttering & re-bar work (T-2) 100% 100% 100%
8 3rd floor roof slab casting work (T-2) 100% 100% 100%
9 2nd floor roof slab casting work (T-3) 100% 100% 100%
10 3rd floor column shuttering-rebar work (T-3) 100% 100% 100%
11 3rd floor column casting work (T-3) 100% 100% 100%

Program for the month of February, 2018

SL. NO. DESCRIPTION OF WORK PROGRAM UPTO THIS MONTH PROGRAM IN THIS MONTH
1 3nd floor roof re-bar & Shuttering work (T-1) 100% 15%
2 3nd floor roof slab casting work (T-1) 100% 100%
3 4TH floor column shuttering-rebar work (T-1) 100% 100%
4 4TH floor column casting work (T-1) 100% 100%
5 4TH floor column shuttering-rebar work (T-2) 100% 100%
6 4TH floor column casting work (T-2) 100% 100%
7 4TH floor roof slab shuttering & re-bar work (T-2) 100% 100%
8 4TH floor roof slab casting work (T-2) 100% 100%
9 3RD floor roof slab casting work (T-3) 100% 100%
10 4TH floor column shuttering-rebar work (T-3) 100% 100%
11 4TH floor column casting work (T-3) 100% 100%

Some of the project picture