Construction Status (February, 2017) – The Signet, Old Chowdhury Para, Comilla

bti - Project Construction Status (7)

Achievement for the month of January, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Inside Plaster work at (Completed up to 7th floor) 8th floor 100% 95% 5%
2 Inside Plaster work at roof top area floor 100% 100% 100%
3 Sanitary internal wiring at all wiring 90% 90% 10%
4 Floor tiles work at all floor 20% 20% 10%
5 Wall tiles fitting at all floor 70% 70% 10%
6 Out side plaster at all floor 85% 85% 10%
7 Electric cable wiring at all floor 30% 30% 5%
8 Window Grill fitting at all floor 50% 50% 25%
9 LCC work (preparation) 10% 10% 10%


Program for the month of  February, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Inside Plaster work at (Completed up to 7th floor) 8th floor 100% 5%
2 Sanitary internal wiring at all floor 95% 5%
3 Floor tiles work at all floor 40% 20%
4 Wall tiles fitting at all floor 85% 15%
5 Out side plaster at all floor 95% 10%
6 Electric cable wiring at all floor 50% 20%
7 Window Grill fitting at all floor 100% 50%
8 Ver. Railing fitting at all floor 75% 75%
9 LCC work (preparation) 100% 90%


Front Image
Some of the project picture

Front view

Bath room wall tiles 5th floor

Bath room wall tiles 5th floor

Brick wall 7th floor

Brick wall 7th floor

Brick wall 8th floor

Brick wall 8th floor

Celling plaster (8th floor)

Selling plaster (8th floor)

Door frame 6th floor

Door frame 6th floor

OHWT

OHWT

Parapet wall

Parapet wall

Sanatary work 6th floor

Sanitary work 6th floor

Out side plaster

Out side plaster