Construction Status (May, 2018) – Summer, Bashundhara, Dhaka

Construction Status

Serial No. Name of work Achievement for the month of March Program  for the month of April
Target Achievement Target  
01 Vertical plumbing lines ( UPVc works) 100% 100%
02 Bath, Kitchen, Floor tiles fittings 100% 100%
03 Windows grill fittings 80% 80% 100%
04 G.Floor Civil works 50% 50% 75%
05 Gas line wiring 70% 70% 100%
06 Stair tiles fitting 80% 80% 100%
07 Paint out side ( Sealer & Putty ) works 50 50 75%
Fire door fittings 100% 100%