Construction Status (February, 2018) – Summer, Bashundhara, Dhaka

Achievement Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 External plaster 100% 80% 30%
2 Toilet wall tiles 70% 70% 20%
3 General floor tiles 60% 60% 40%
4 LCC 90% 50% 50%
Vertical Plumbing lines 40% 40%
Stair, Lobby plaster 100% 100%
7 GF casting 50% 50% 50%

Program for the month of February, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 External plaster 100% 20%
2 Toilet wall tiles 100% 30%
3 General floor tiles 100% 40%
4 LCC 100% 10%
Vertical plumbing lines 80% 40%
5 Roof top wiring 40% 40%
7 GF casting 100% 50%