Construction Status (February, 2018) –SANCTUM, Eskaton, Dhaka

Achievement Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 Earth work 100% 60% 60%
2 Foundation works up to Grade beam 100% 60% 60%
3 GF Column 25% 0% 0%

Program for the month of February, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Earth work 100% 40%
2 Foundation works up to Grade beam 100% 40%
3 GF Column 100% 100%
4 GF Roof shuttering 100% 100%