Construction Status (February, 2018) – Southern Heights, Uttara, Dhaka

Achievement Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 8th floor Column and slab casting 100% 100% 100%
2 9th floor column casting 100% 100% 100%
3 1st, 5th, 6th floor Brickwork 70% 70% 70%
4 Ceiling plaster -5th, 6th floor 100% 100% 100%
5 Ancilary works-2nd, 3rd, 4th floor 100% 100% 100%
6 Electrical MK box setting-2nd, 3rd, 4th floor 100% 100% 100%

Program for the month of February, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Roof top RCC works for OWT, Machine room, Parapet,etc 80% 80%
3 1st, 2nd, 3rd floor brick work 100% 30%
4 Inside plaster-1st,2nd floor 70% 70%
5 Ancilary works-2nd, 3rd, 4th floor 100% 100%
6 Electrical MK box setting-2nd, 3rd, 4th floor 100% 100%
7 Electrical conduiting-1st, 2nd, 6th floor 80% 80%
8 Sanitary conduiting-4th floor 100% 100%
9 Ancilary works-1st, 2nd floor 100% 100%

Some of the project picture