Construction Status (April, 2018) – Southern Heights, Uttara, Dhaka

Construction Status

Serial No. Name of work Achievement Up to month March, 2018 Program  Up to month April, 2018
Target Achievement Target  
01 RCC works for OHWT, Machine room & Parapet wall 100% 70% 100%
02 Block Works (4th , 5th & 6th floor) 100% 100%
03 Inside Plaster works (3rd & 4th Floor) 60% 40%
04 Ancillary  works (5th , 6th & 7th floor) 70% 70%
05 Elec. MK box fitting (2nd , 3rd & 4th floor) 100% 100%
06 Ancillary works (3rd & 4th Floor) 100% 100%
07 Door frame fixing (1st , 2nd & 3rd floor) 70% 70%
08 Block Works (7th , 8th & 9th floor) 80%
09 Inside wall Plaster (1st , 2nd , 3rd , 4th , 5th floor) 80%
10 Ancillary works (8th & 9th Floor) 100%
11

 

Elec. Conduit Pipe (7th & 8th Floor) 100%
12 Door frame fitting (4th, 5th , 6th & 7th floor) 100%
13 Sanitary PPR wiring (2nd , 3rd , 4th floor) 80%